4029 N GOODLAND AVE 91604
Certificate Information: 4029 N GOODLAND AVE 91604
- Application / Permit
- 20047-20000-00172
- Plan Check / Job No.
- B20VN01885
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 32' x 15' SWIMMING POOL WITH 6' x 6' SPA PER STANDARD PLAN #270 AND ENGINEER DESIGN
- Permit Issued
- Issued on 3/26/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | ROSENDO MEDINA |
| Corrections Issued | 3/4/2020 | ROSENDO MEDINA |
| Quality Review Completed | 3/12/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/16/2020 | APPLICANT |
| Plan Check Approved | 3/26/2020 | ROSENDO MEDINA |
| Issued | 3/26/2020 | LADBS |
| CofO in Progress | 8/11/2020 | ARAM AVEDISIAN |
| CofO in Progress | 8/11/2020 | ARAM AVEDISIAN |
| Permit Finaled | 4/9/2021 | DANIEL ORRANTE |
| CofO Issued | 4/9/2021 | DANIEL ORRANTE |
| Permit Finaled | 4/9/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/4/2020 | ROSENDO MEDINA |
Contact Information
| Contractor | Imagine Builders Inc; Lic. No.: 923469-B | 18034 VENTURA BLVD #307 ENCINO, CA 91316 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
| Engineer | Miller,, Karen Lynn; Lic. No.: GE2257 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deck | 4/28/2020 | Corrections Issued | DAVID SANDOVAL |
| Pre-Gunite | 4/28/2020 | Approved | DAVID SANDOVAL |
| Enclosure/Fence | 6/3/2020 | Corrections Issued | ARAM AVEDISIAN |
| Enclosure/Fence | 6/4/2020 | Approved | ARAM AVEDISIAN |
| Pool Equipment Noise Test | 6/9/2020 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 6/10/2020 | Approved | ARAM AVEDISIAN |
| Final | 6/10/2020 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 6/10/2020 | SGSOV Approved | ARAM AVEDISIAN |
| Final | 6/11/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 8/11/2020 | OK to Issue CofO | ARAM AVEDISIAN |