11958 W WAGNER ST 90230

Certificate Information: 11958 W WAGNER ST 90230

Application / Permit
20047-20000-00162
Plan Check / Job No.
B20VN01805
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA PER STANDARD PLAN #268
Permit Issued
Issued on 2/4/2020
Issuing Office
Valley
Current Status
CofO Issued on 3/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2020 APPLICANT
Assigned to Plan Check Engineer 2/4/2020 YAQUB MIRZA
Plan Check Approved 2/4/2020 YAQUB MIRZA
Issued 2/4/2020 LADBS
CofO in Progress 3/16/2023 JESUS RODRIGUEZ
Permit Finaled 3/21/2023 DANIEL ORRANTE
CofO Issued 3/21/2023 DANIEL ORRANTE
Permit Finaled 3/21/2023 DANIEL ORRANTE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Flexi - Tech Contracting Inc; Lic. No.: 767683-C53 6924 CANBY AVENUE UNIT 105      RESEDA, CA 91335
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/13/2020 Not Ready for Inspection CRAIG DAVIS
Pre-Gunite 2/13/2020 Not Ready for Inspection CRAIG DAVIS
Pre-Gunite 2/24/2020 Approved DAVID FEILER
Rough-Electrical 2/24/2020 Partial Approval DAVID FEILER
Deputy Shotcrete 2/27/2020 Conditional Approval CRAIG DAVIS
Deputy Shotcrete 2/27/2020 No Access for Inspection CRAIG DAVIS
Deputy Shotcrete 2/28/2020 Conditional Approval DAVID FEILER
Gas Piping or Gas Test 3/27/2020 Partial Approval DAVID FEILER
Rough-Electrical 3/27/2020 Partial Approval DAVID FEILER
Rough-Plumbing 3/27/2020 Partial Approval DAVID FEILER
Deck 4/30/2020 Approved JUAN VALENZUELA
Gas Piping or Gas Test 4/30/2020 Approved JUAN VALENZUELA
Enclosure/Fence 6/2/2020 Approved JOHNNY MIRANDA
Equipment Noise Level 6/10/2020 Approved STEVEN BELTRAN
Excavation/Setback/Form/Re-Bar 6/12/2020 Approved EVAN COOPER
Final 6/12/2020 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/12/2020 SGSOV Approved EVAN COOPER
Final 9/8/2020 Corrections Issued JOHNNY MIRANDA
Final 9/10/2020 Conditional Approval EVAN COOPER
Final 3/15/2023 OK to Issue CofO JESUS RODRIGUEZ