4411 N CONCHITA WAY 91356

Certificate Information: 4411 N CONCHITA WAY 91356

Application / Permit
20047-20000-00159
Plan Check / Job No.
B20VN01795
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
RELOCATE 8'X8' SPA FROM NORTH OF POOL TO SOUTH OF POOL PER ENGINEERING
Permit Issued
Issued on 2/4/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/29/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2020 APPLICANT
Assigned to Plan Check Engineer 2/4/2020 SERGIO MUNIZ
Corrections Issued 2/4/2020 SERGIO MUNIZ
Plan Check Approved 2/4/2020 SEAN SHAHMIRI
Issued 2/4/2020 LADBS
CofO in Progress 8/12/2020 DAVID SANDOVAL
Permit Finaled 9/29/2020 DONALD SUNSERI
CofO Issued 9/29/2020 DONALD SUNSERI
Permit Finaled 9/29/2020 DONALD SUNSERI

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/4/2020 SERGIO MUNIZ
Tract Map conditions Cleared 2/4/2020 VINCENT QUITORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/7/2020 Approved DAVID SANDOVAL
Pre-Gunite 4/30/2020 Approved DAVID SANDOVAL
Gas Piping or Gas Test 5/19/2020 Approved DAVID SANDOVAL
Rough-Mechanical 5/19/2020 Not Ready for Inspection DAVID SANDOVAL
Deck 5/29/2020 Approved DAVID SANDOVAL
Enclosure/Fence 6/3/2020 Corrections Issued DAVID SANDOVAL
Enclosure/Fence 6/5/2020 Approved DAVID SANDOVAL
Pool Equipment Noise Test 6/18/2020 Approved FELIPE PENICHE
Excavation/Setback/Form/Re-Bar 6/24/2020 Approved DAVID SANDOVAL
Final 6/24/2020 Corrections Issued DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 6/24/2020 SGSOV Approved DAVID SANDOVAL
Final 7/6/2020 Partial Approval DAVID SANDOVAL
Final 8/12/2020 OK to Issue CofO DAVID SANDOVAL