1065 N CHANTILLY ROAD 90077

Certificate Information: 1065 N CHANTILLY ROAD 90077

Application / Permit
20047-20000-00130
Plan Check / Job No.
B20VN01484
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW (17'-0"x 32'-6") IRREGULLAR SHAPE SWIMMING POOL WITH (6'-4"x 8'-2") SPA. WORK PER ENGINEER.
Permit Issued
Issued on 3/15/2021
Issuing Office
Current Status
CofO Issued on 10/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 TROY DEGUZMAN
Corrections Issued 3/10/2020 TROY DEGUZMAN
Quality Review Completed 3/16/2020 CHON CHIO KUO
Building Plans Picked Up 4/8/2020 APPLICANT
Applicant returned to address corrections 10/19/2020 TROY DEGUZMAN
Applicant returned to address corrections 1/6/2021 TROY DEGUZMAN
Plan Check Approved 2/23/2021 TROY DEGUZMAN
Issued 3/15/2021 APPLICANT
CofO in Progress 10/6/2022 CHRISTOPHER WILSON
CofO in Progress 10/6/2022 CHRISTOPHER WILSON
Permit Finaled 10/19/2022 DANIEL ORRANTE
CofO Issued 10/19/2022 DANIEL ORRANTE
Permit Finaled 10/19/2022 DANIEL ORRANTE

Permit Application Clearance Information

GPI Written Notices Cleared 10/19/2020 TROY DEGUZMAN
Grading Pre-Inspection Cleared 10/19/2020 TROY DEGUZMAN

Contact Information

Contractor Bel Air Builders Inc; Lic. No.: 872640-B 17220 SUNBURST STREET      NORTHRIDGE, CA 91325
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401
Geologist Barrett,, Mark A; Lic. No.: EG2088 14428 HAMLIN ST 200      VAN NUYS, CA 91401

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grounding or Bonding 9/3/2021 Partial Approval CHRISTOPHER WILSON
Pool Piping 9/3/2021 Approved CHRISTOPHER WILSON
Pre-Gunite 9/3/2021 Approved CHRISTOPHER WILSON
Rough-Electrical 9/3/2021 Partial Approval CHRISTOPHER WILSON
Rough-Plumbing 9/3/2021 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 9/9/2021 Conditional Approval CHRISTOPHER WILSON
Rough-Plumbing 10/14/2021 Corrections Issued CHRISTOPHER WILSON
Gas Piping or Gas Test 1/6/2022 Corrections Issued CHRISTOPHER WILSON
Rough-Plumbing 1/6/2022 Not Ready for Inspection CHRISTOPHER WILSON
Gas Piping or Gas Test 1/19/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Final 1/19/2022 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 6/10/2022 Partial Approval CHRISTOPHER WILSON
Enclosure/Fence 7/18/2022 Corrections Issued CHRISTOPHER WILSON
Pre-Inspection 7/25/2022 Not Ready for Inspection CHRISTOPHER WILSON
Enclosure/Fence 8/3/2022 Approved CHRISTOPHER WILSON
Pool Equipment Noise Test 9/20/2022 Approved JUSTIN CURTIS
Excavation/Setback/Form/Re-Bar 9/23/2022 Approved CHRISTOPHER WILSON
Final 9/23/2022 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Approved CHRISTOPHER WILSON
Final 10/3/2022 Corrections Issued CHRISTOPHER WILSON
Final 10/5/2022 OK to Issue CofO CHRISTOPHER WILSON