1065 N CHANTILLY ROAD 90077
Certificate Information: 1065 N CHANTILLY ROAD 90077
- Application / Permit
- 20047-20000-00130
- Plan Check / Job No.
- B20VN01484
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW (17'-0"x 32'-6") IRREGULLAR SHAPE SWIMMING POOL WITH (6'-4"x 8'-2") SPA. WORK PER ENGINEER.
- Permit Issued
- Issued on 3/15/2021
- Issuing Office
- Current Status
- CofO Issued on 10/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | TROY DEGUZMAN |
| Corrections Issued | 3/10/2020 | TROY DEGUZMAN |
| Quality Review Completed | 3/16/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 4/8/2020 | APPLICANT |
| Applicant returned to address corrections | 10/19/2020 | TROY DEGUZMAN |
| Applicant returned to address corrections | 1/6/2021 | TROY DEGUZMAN |
| Plan Check Approved | 2/23/2021 | TROY DEGUZMAN |
| Issued | 3/15/2021 | APPLICANT |
| CofO in Progress | 10/6/2022 | CHRISTOPHER WILSON |
| CofO in Progress | 10/6/2022 | CHRISTOPHER WILSON |
| Permit Finaled | 10/19/2022 | DANIEL ORRANTE |
| CofO Issued | 10/19/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/19/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 10/19/2020 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 10/19/2020 | TROY DEGUZMAN |
Contact Information
| Contractor | Bel Air Builders Inc; Lic. No.: 872640-B | 17220 SUNBURST STREET NORTHRIDGE, CA 91325 |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
| Engineer | Walter,, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
| Geologist | Barrett,, Mark A; Lic. No.: EG2088 | 14428 HAMLIN ST 200 VAN NUYS, CA 91401 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 9/3/2021 | Partial Approval | CHRISTOPHER WILSON |
| Pool Piping | 9/3/2021 | Approved | CHRISTOPHER WILSON |
| Pre-Gunite | 9/3/2021 | Approved | CHRISTOPHER WILSON |
| Rough-Electrical | 9/3/2021 | Partial Approval | CHRISTOPHER WILSON |
| Rough-Plumbing | 9/3/2021 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 9/9/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Rough-Plumbing | 10/14/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Gas Piping or Gas Test | 1/6/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Rough-Plumbing | 1/6/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Gas Piping or Gas Test | 1/19/2022 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Final | 1/19/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Inspection | 6/10/2022 | Partial Approval | CHRISTOPHER WILSON |
| Enclosure/Fence | 7/18/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Inspection | 7/25/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Enclosure/Fence | 8/3/2022 | Approved | CHRISTOPHER WILSON |
| Pool Equipment Noise Test | 9/20/2022 | Approved | JUSTIN CURTIS |
| Excavation/Setback/Form/Re-Bar | 9/23/2022 | Approved | CHRISTOPHER WILSON |
| Final | 9/23/2022 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 9/23/2022 | SGSOV Approved | CHRISTOPHER WILSON |
| Final | 10/3/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Final | 10/5/2022 | OK to Issue CofO | CHRISTOPHER WILSON |