8316 W SKYLINE DR 90046
Certificate Information: 8316 W SKYLINE DR 90046
- Application / Permit
- 20047-20000-00084
- Plan Check / Job No.
- B20VN00904
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 34' X 14' POOL WITH 7'X 7' SPA ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/11/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 1/24/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 2/7/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 2/11/2020 | APPLICANT |
| Applicant returned to address corrections | 3/5/2020 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 3/11/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 3/11/2020 | LADBS |
| CofO in Progress | 4/16/2021 | RAUL BARAJAS |
| Permit Finaled | 5/8/2021 | DEROLD HAUFF |
| Permit Finaled | 5/8/2021 | DEROLD HAUFF |
| CofO Issued | 5/8/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Specific Plan | Cleared | 2/21/2020 | ANNA VIDAL |
| ZA Case | Cleared | 2/21/2020 | ANNA VIDAL |
| Grading Pre-Inspection | Cleared | 3/5/2020 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | Shimizu Curtis; Lic. No.: 901908-C53 | 5541 WEST 123RD PLACE HAWTHORNE, CA 90250 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 6/12/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Grounding or Bonding | 6/12/2020 | Approved | RAUL BARAJAS |
| Pre-Gunite | 6/12/2020 | Conditional Approval | RAUL BARAJAS |
| Rough-Electrical | 6/12/2020 | Partial Approval | RAUL BARAJAS |
| Rough-Plumbing | 6/12/2020 | Approved | RAUL BARAJAS |
| Deputy Shotcrete | 6/22/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Deck | 7/15/2020 | Approved | JOSEPH MCGARRY |
| Enclosure/Fence | 8/10/2020 | Approved | RAUL BARAJAS |
| Final | 10/16/2020 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 10/16/2020 | SGSOV Not Ready | RAUL BARAJAS |
| Pool Equipment Noise Test | 10/19/2020 | Approved | ROBERT CHAVEZ |
| Final | 10/23/2020 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 10/23/2020 | SGSOV Approved | RAUL BARAJAS |
| Final | 4/16/2021 | OK to Issue CofO | RAUL BARAJAS |