19426 W ROSCOE BLVD 91324
Certificate Information: 19426 W ROSCOE BLVD 91324
- Application / Permit
- 20047-20000-00064
- Plan Check / Job No.
- B20VN00688
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 15' X 25' POOL PER STD PLAN 268.
- Permit Issued
- Issued on 6/2/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/13/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | PINANK PATEL |
| Plan Check Approved | 1/16/2020 | PINANK PATEL |
| Issued | 6/2/2020 | LADBS |
| CofO in Progress | 9/30/2020 | VINCENT HANLEY |
| CofO Issued | 10/13/2020 | DONALD SUNSERI |
| Permit Finaled | 10/13/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1499 IRIS GROVE DR CORONA, CA 92881 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/5/2020 | Approved | VINCENT HANLEY |
| Deputy Shotcrete | 6/15/2020 | Conditional Approval | MICHAEL TEMPLE |
| Enclosure/Fence | 7/22/2020 | Approved | VINCENT HANLEY |
| Grounding or Bonding | 7/22/2020 | Approved | VINCENT HANLEY |
| Pre-Inspection | 8/19/2020 | No Access for Inspection | VINCENT HANLEY |
| Pool Equipment Noise Test | 8/20/2020 | No Access for Inspection | ALFREDO FLORES |
| Pool Equipment Noise Test | 8/31/2020 | Approved | ALFREDO FLORES |
| Equipment Noise Level | 9/1/2020 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 9/15/2020 | No Access for Inspection | VINCENT HANLEY |
| Final | 9/15/2020 | No Access for Inspection | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/15/2020 | SGSOV Not Ready | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 9/23/2020 | Approved | VINCENT HANLEY |
| Final | 9/23/2020 | OK to Issue CofO | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/23/2020 | SGSOV Approved | VINCENT HANLEY |