4219 N CAMELLIA AVE 91604
Certificate Information: 4219 N CAMELLIA AVE 91604
- Application / Permit
- 20047-20000-00028
- Plan Check / Job No.
- B20VN00266
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16' X 22' POOL W/ 6' X 6' SPA PER LA CITY STANDARD PLAN #268
- Permit Issued
- Issued on 6/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2020 | ARTIN ZARUKIAN |
| Corrections Issued | 1/8/2020 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 3/6/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 5/4/2020 | LUIS RINCON |
| Plan Check Approved | 6/2/2020 | JENNIFER LEE |
| Issued | 6/3/2020 | LADBS |
| CofO in Progress | 9/21/2020 | CHRISTOPHE COCHRAN |
| CofO in Progress | 9/21/2020 | CHRISTOPHE COCHRAN |
| Permit Finaled | 2/6/2021 | MICHAEL SMITH |
| CofO Issued | 2/6/2021 | MICHAEL SMITH |
| Permit Finaled | 2/6/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/26/2020 | ERNEST FRESQUEZ |
Contact Information
| Contractor | Pool Logic La; Lic. No.: 1053685-C53 | 1276 E COLORADO BLVD PASADENA, CA 91106 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 6/11/2020 | Approved | JEFFREY PARD |
| Deputy Shotcrete | 6/12/2020 | Approved | JEFFREY PARD |
| Deck | 6/17/2020 | Partial Approval | THOMAS FINNILA |
| Deck | 6/30/2020 | Approved | DANIEL DREW |
| Enclosure/Fence | 7/27/2020 | Approved | THOMAS FINNILA |
| Equipment Noise Level | 8/7/2020 | Approved | FELIPE PENICHE |
| Pool Equipment Noise Test | 8/7/2020 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 8/10/2020 | Approved | THOMAS FINNILA |
| Final | 8/10/2020 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/10/2020 | SGSOV Approved | THOMAS FINNILA |
| Final | 8/13/2020 | OK to Issue CofO | THOMAS FINNILA |