11539 W DUQUE DR 91604

Certificate Information: 11539 W DUQUE DR 91604

Application / Permit
20047-20000-00001
Plan Check / Job No.
B20VN00014
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 25'-0" X 15'-0" SWIMMING POOL WITH 6'-0" X 6'-0" SPA PER STD PLAN # 268.
Permit Issued
Issued on 2/7/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/31/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2020 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 ARTIN ZARUKIAN
Corrections Issued 1/2/2020 ARTIN ZARUKIAN
Plan Check Approved 2/7/2020 SARKIS HARABEDIAN
Issued 2/7/2020 LADBS
CofO in Progress 10/5/2020 ARAM AVEDISIAN
Permit Finaled 10/31/2020 MICHAEL SMITH
CofO Issued 10/31/2020 MICHAEL SMITH
Permit Finaled 10/31/2020 MICHAEL SMITH

Permit Application Clearance Information

Specific Plan Cleared 1/2/2020 STEVEN WECHSLER
ZI Cleared 2/7/2020 HERMINIGILDO AGUSTIN

Contact Information

Contractor Athlon Pool Company Inc; Lic. No.: 970093-C53 150 S GLENOAKS BLVD #9152      BURBANK, CA 91502
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/2/2020 Not Ready for Inspection ARAM AVEDISIAN
Grounding or Bonding 4/2/2020 Partial Approval ARAM AVEDISIAN
Pool Piping 4/2/2020 Approved ARAM AVEDISIAN
Pre-Gunite 4/2/2020 Not Ready for Inspection ARAM AVEDISIAN
Deck 6/9/2020 Not Ready for Inspection ARAM AVEDISIAN
Gas Piping or Gas Test 6/9/2020 Not Ready for Inspection ARAM AVEDISIAN
Grounding or Bonding 6/9/2020 Not Ready for Inspection ARAM AVEDISIAN
Pool Piping 6/9/2020 Not Ready for Inspection ARAM AVEDISIAN
Pre-Gunite 6/9/2020 Not Ready for Inspection ARAM AVEDISIAN
Rough-Electrical 6/9/2020 Not Ready for Inspection ARAM AVEDISIAN
Rough-Plumbing 6/9/2020 Not Ready for Inspection ARAM AVEDISIAN
Deck 6/10/2020 Approved ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 6/10/2020 Approved ARAM AVEDISIAN
Grounding or Bonding 6/10/2020 Approved ARAM AVEDISIAN
Pool Piping 6/10/2020 Approved ARAM AVEDISIAN
Pre-Gunite 6/10/2020 Approved ARAM AVEDISIAN
Rough-Electrical 6/10/2020 Approved ARAM AVEDISIAN
Deck 8/11/2020 Approved ARAM AVEDISIAN
Enclosure/Fence 8/12/2020 Approved ARAM AVEDISIAN
Final 9/4/2020 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/4/2020 SGSOV Approved ARAM AVEDISIAN
Final 10/5/2020 OK to Issue CofO ARAM AVEDISIAN