12009 N CARABELA CT 91326

Certificate Information: 12009 N CARABELA CT 91326

Application / Permit
20047-10001-02363
Plan Check / Job No.
B21LA06120
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
SUP TO 20047-10001-02363 "NEW POOL AND SPA PER STANDARD DETAIL #268 AND DETAIL #501" TO ADD POOL COVER CHANGE SIZE OF POOL AND SPA, CHANGE SET BACKS.
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
Permit Finaled on 6/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 RACHEL BEYENE
Corrections Issued 4/8/2021 RACHEL BEYENE
Issued 4/22/2021 APPLICANT
Permit Finaled 7/23/2021 DAVID SCANTLIN
Refund in Progress 1/5/2022 TERENCE SHIA
Refund Closed 1/5/2022 TERENCE SHIA
Permit Finaled 1/5/2022 TERENCE SHIA
Refund in Progress 4/19/2022 EMILY HU
Refund Denied 6/30/2022 EMILY HU
Permit Finaled 6/30/2022 EMILY HU

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-B 15021 VENTURA BLVD STE 520      SHERMAN OAKS, CA 91403
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Enclosure/Fence 6/24/2021 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 6/24/2021 Approved DAVID SCANTLIN
Gas Piping or Gas Test 6/24/2021 Approved DAVID SCANTLIN
Grading Pre-Inspection 6/24/2021 Approved DAVID SCANTLIN
Grounding or Bonding 6/24/2021 Approved DAVID SCANTLIN
Gunite 6/24/2021 Approved DAVID SCANTLIN
Pool Piping 6/24/2021 Approved DAVID SCANTLIN
Posting Pre-Inspection 6/24/2021 Approved DAVID SCANTLIN
Pre-Gunite 6/24/2021 Approved DAVID SCANTLIN
Pre-Inspection 6/24/2021 Approved DAVID SCANTLIN
Rough-Electrical 6/24/2021 Approved DAVID SCANTLIN
Rough-Plumbing 6/24/2021 Approved DAVID SCANTLIN
Equipment Noise Level 7/21/2021 Approved ALFREDO FLORES
Final 7/21/2021 Partial Approval DAVID SCANTLIN