2034 N CASTILIAN DR 90068

Certificate Information: 2034 N CASTILIAN DR 90068

Application / Permit
20047-10000-02314
Plan Check / Job No.
B20LA23740
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) POOL AND SPA.
Permit Issued
Issued on 6/17/2021
Issuing Office
Current Status
CofO Issued on 12/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 HERNAN ARREOLA
Corrections Issued 1/7/2021 HERNAN ARREOLA
Quality Review Completed 1/14/2021 ALLEN MANALANSAN
Building Plans Picked Up 1/19/2021 APPLICANT
Applicant returned to address corrections 3/30/2021 HERNAN ARREOLA
Applicant returned to address corrections 6/2/2021 HERNAN ARREOLA
Plan Check Approved 6/17/2021 HERNAN ARREOLA
Issued 6/17/2021 APPLICANT
CofO in Progress 12/23/2023 BRIAN SULLIVAN
Permit Finaled 12/28/2023 DEROLD HAUFF
CofO Issued 12/28/2023 DEROLD HAUFF
Permit Finaled 12/28/2023 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 6/3/2021 OLGA AYALA

Contact Information

Contractor Owner-Builder       ,
Engineer Le,, Thang Huu; Lic. No.: C63174 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Geologist Triebold,, Mark John; Lic. No.: EG1796 6906 QUITO COURT      CAMARILLO, CA 93012

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/2/2021 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 12/10/2021 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 2/14/2022 Partial Approval BRIAN SULLIVAN
Deputy Other (see comments) 2/16/2022 Conditional Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/19/2022 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/25/2022 Approved BRIAN SULLIVAN
Deputy Other (see comments) 4/27/2022 Conditional Approval BRIAN SULLIVAN
Enclosure/Fence 11/14/2022 Approved RAUL BARAJAS
Final 4/5/2023 Corrections Issued BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Approved BRIAN SULLIVAN
Final 6/21/2023 Corrections Issued BRIAN SULLIVAN
Final 12/23/2023 OK to Issue CofO BRIAN SULLIVAN