3211 S SHELBY DR 90034

Certificate Information: 3211 S SHELBY DR 90034

Application / Permit
20047-10000-02270
Plan Check / Job No.
B20LA23354
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA PER STANDARD PLAN # 268 AND DETAIL #400-60
Permit Issued
Issued on 9/14/2021
Issuing Office
Current Status
CofO Issued on 7/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 SINA KHOSRAVI
Corrections Issued 12/27/2020 SINA KHOSRAVI
Building Plans Picked Up 6/4/2021 APPLICANT
Plan Check Approved 8/24/2021 RICARDO RAMIREZ
Issued 9/14/2021 APPLICANT
CofO in Progress 6/29/2022 KEVIN SARGSYAN
Permit Finaled 7/8/2022 DANIEL ORRANTE
CofO Issued 7/8/2022 DANIEL ORRANTE
Permit Finaled 7/8/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/27/2020 SINA KHOSRAVI
Construction near power lines Cleared 8/10/2021 TINA MIRANDA

Contact Information

Contractor Coastal Aquatic Creations; Lic. No.: 697943-C53 149 SOUTH BARRINGTON AVE #158      LOS ANGELES, CA 90049
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/5/2022 Corrections Issued KEVIN SARGSYAN
Pre-Gunite 1/5/2022 Not Ready for Inspection KEVIN SARGSYAN
Pool Piping 1/10/2022 Partial Approval KEVIN SARGSYAN
Pre-Gunite 1/10/2022 Conditional Approval KEVIN SARGSYAN
Rough-Electrical 1/10/2022 Partial Approval KEVIN SARGSYAN
Rough-Plumbing 1/10/2022 Partial Approval KEVIN SARGSYAN
Deputy Shotcrete 1/11/2022 Conditional Approval KEVIN SARGSYAN
Gas Piping or Gas Test 1/18/2022 Corrections Issued KEVIN SARGSYAN
Rough-Electrical 1/18/2022 Not Ready for Inspection KEVIN SARGSYAN
Rough-Plumbing 1/18/2022 Corrections Issued KEVIN SARGSYAN
Gas Piping or Gas Test 1/25/2022 Partial Approval KEVIN SARGSYAN
Pool Piping 1/25/2022 Approved KEVIN SARGSYAN
Rough-Electrical 1/25/2022 Approved KEVIN SARGSYAN
Rough-Plumbing 1/25/2022 Approved KEVIN SARGSYAN
Deck 3/15/2022 Approved KEVIN SARGSYAN
Enclosure/Fence 6/1/2022 Approved KEVIN SARGSYAN
Pool Equipment Noise Test 6/14/2022 Approved ROBERT CHAVEZ
Final 6/28/2022 OK to Issue CofO KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 6/28/2022 SGSOV Approved KEVIN SARGSYAN