159 N MABERY ROAD 90402

Certificate Information: 159 N MABERY ROAD 90402

Application / Permit
20047-10000-02264
Plan Check / Job No.
B20LA23262
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) SWIMMING POOL & SPA W/DECK
Permit Issued
Issued on 4/28/2021
Issuing Office
Current Status
CofO Issued on 8/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2020 APPLICANT
Assigned to Plan Check Engineer 12/17/2020 PRANITA SHAH
Corrections Issued 12/28/2020 PRANITA SHAH
Quality Review Completed 1/12/2021 WING SUEN
Building Plans Picked Up 1/19/2021 APPLICANT
Plan Check Approved 4/28/2021 LAMAR DAVIS
Issued 4/28/2021 APPLICANT
CofO in Progress 8/2/2024 ARAM AVEDISIAN
Permit Finaled 8/14/2024 RICHARD STEINBACH
CofO Issued 8/14/2024 RICHARD STEINBACH
Permit Finaled 8/14/2024 RICHARD STEINBACH

Permit Application Clearance Information

Coastal Zone Cleared 3/5/2021 MIGUEL GAMBOA
ZA Case Cleared 3/5/2021 MIGUEL GAMBOA
Miscellaneous Cleared 3/15/2021 MIGUEL GAMBOA
Sewer availability Cleared 3/16/2021 CATHERINE ADROVER
GPI Written Notices Cleared 3/19/2021 LAMAR DAVIS
Grading Pre-Inspection Cleared 3/19/2021 MATTHEW JENKINS
Eng Process Fee Ord 176,300 Cleared 3/22/2021 CATHERINE ADROVER
Low Impact Development Cleared 4/22/2021 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 4/27/2021 CATHERINE ADROVER

Contact Information

Contractor Bruder Construction Inc; Lic. No.: 700657-B 286 BELL CANYON ROAD      BELL CANYON, CA 91307

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Enclosure/Fence 5/30/2024 Corrections Issued ARAM AVEDISIAN
Enclosure/Fence 6/4/2024 Approved ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 6/4/2024 Approved ARAM AVEDISIAN
Grounding or Bonding 6/4/2024 Partial Approval ARAM AVEDISIAN
Pool Piping 6/4/2024 Approved ARAM AVEDISIAN
Pre-Gunite 6/4/2024 Approved ARAM AVEDISIAN
Grounding or Bonding 6/6/2024 Approved ARAM AVEDISIAN
Final 7/29/2024 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Approved ARAM AVEDISIAN
Final 8/2/2024 OK to Issue CofO ARAM AVEDISIAN