1958 N AVON ST 90026
Certificate Information: 1958 N AVON ST 90026
- Application / Permit
- 20047-10000-02155
- Plan Check / Job No.
- B20LA22226
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL AND SPA PER ENGINEER DESIGN
- Permit Issued
- Issued on 6/12/2021
- Issuing Office
- Current Status
- CofO Issued on 9/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | HERNAN ARREOLA |
| Corrections Issued | 1/13/2021 | HERNAN ARREOLA |
| Quality Review Completed | 1/28/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 2/1/2021 | APPLICANT |
| Plan Check Approved | 6/7/2021 | HERNAN ARREOLA |
| Issued | 6/12/2021 | APPLICANT |
| CofO in Progress | 9/12/2021 | THOMAS LOGRASSO |
| CofO in Progress | 9/12/2021 | THOMAS LOGRASSO |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
| CofO Issued | 9/29/2021 | DEROLD HAUFF |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/7/2021 | HERNAN ARREOLA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Kolodziej,, Kenneth James; Lic. No.: C64768 | 400 EAST ESTHER PL PLACENTIA, CA 92870 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/21/2021 | Partial Approval | SCOTT FINNILA |
| Deck | 7/23/2021 | Off-Hour Fees Due | |
| ELECTRICAL-Final | 7/23/2021 | Off-Hour Fees Due | |
| Enclosure/Fence | 7/23/2021 | Off-Hour Fees Due | |
| Equipment Noise Level | 7/23/2021 | Off-Hour Fees Due | |
| Gas Piping or Gas Test | 7/23/2021 | Off-Hour Fees Due | |
| Grading Pre-Inspection | 7/23/2021 | Off-Hour Fees Due | |
| Grounding or Bonding | 7/23/2021 | Off-Hour Fees Due | |
| Gunite | 7/23/2021 | Off-Hour Fees Due | |
| PLUMBING-Final | 7/23/2021 | Off-Hour Fees Due | |
| Piling/Pier/Caisson | 7/23/2021 | Off-Hour Fees Due | |
| Pool Equipment Noise Test | 7/23/2021 | Off-Hour Fees Due | |
| Pool Piping | 7/23/2021 | Off-Hour Fees Due | |
| Pool/Spa Cover | 7/23/2021 | Off-Hour Fees Due | |
| Posting Pre-Inspection | 7/23/2021 | Off-Hour Fees Due | |
| Pre-Inspection | 7/23/2021 | Off-Hour Fees Due | |
| Rough-Electrical | 7/23/2021 | Off-Hour Fees Due | |
| Rough-Plumbing | 7/23/2021 | Off-Hour Fees Due | |
| SGSOV-Seismic Gas S/O Valve | 7/23/2021 | Off-Hour Fees Due | |
| Solar System | 7/23/2021 | Off-Hour Fees Due | |
| Special/Order Compliance | 7/23/2021 | Off-Hour Fees Due | |
| Deck | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Enclosure/Fence | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Equipment Noise Level | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Gas Piping or Gas Test | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Grading Pre-Inspection | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Grounding or Bonding | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Gunite | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Final | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Pool Equipment Noise Test | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Pool Piping | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Pool/Spa Cover | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Posting Pre-Inspection | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Pre-Inspection | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Rough-Electrical | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Rough-Plumbing | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 7/27/2021 | SGSOV Not Ready | THOMAS LOGRASSO |
| Solar System | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Special/Order Compliance | 7/27/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Grounding or Bonding | 7/30/2021 | Partial Approval | THOMAS LOGRASSO |
| Pre-Gunite | 7/30/2021 | Corrections Issued | THOMAS LOGRASSO |
| Rough-Electrical | 7/30/2021 | Approved | THOMAS LOGRASSO |
| Rough-Plumbing | 7/30/2021 | Approved | THOMAS LOGRASSO |
| Grounding or Bonding | 8/12/2021 | Approved | THOMAS LOGRASSO |
| Enclosure/Fence | 8/23/2021 | Approved | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 8/30/2021 | Approved | THOMAS LOGRASSO |
| Final | 8/30/2021 | Corrections Issued | THOMAS LOGRASSO |
| Pre-Gunite | 8/30/2021 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/30/2021 | SGSOV Approved | THOMAS LOGRASSO |
| Pool Equipment Noise Test | 9/8/2021 | Approved | ROBERT CHAVEZ |
| Final | 9/10/2021 | OK to Issue CofO | THOMAS LOGRASSO |