3218 W ATWATER AVE 90039
Certificate Information: 3218 W ATWATER AVE 90039
- Application / Permit
- 20047-10000-02061
- Plan Check / Job No.
- B20LA21331
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL PER STANDARD PLAN
- Permit Issued
- Issued on 2/8/2021
- Issuing Office
- Current Status
- CofO Issued on 9/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2020 | ZAW HAN |
| Corrections Issued | 12/8/2020 | ZAW HAN |
| Plan Check Approved | 1/25/2021 | RICARDO RAMIREZ |
| Issued | 2/8/2021 | APPLICANT |
| Building Plans Picked Up | 2/11/2021 | APPLICANT |
| CofO in Progress | 8/21/2021 | SCOTT FINNILA |
| Permit Finaled | 9/2/2021 | DEROLD HAUFF |
| CofO Issued | 9/2/2021 | DEROLD HAUFF |
| Permit Finaled | 9/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/15/2021 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 1/15/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 1/15/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Intex Design And Construction Inc; Lic. No.: 981718-B | 15021 VENTURA BLVD STE 520 SHERMAN OAKS, CA 91403 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 4/29/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Gunite | 4/29/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Rough-Electrical | 4/29/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Rough-Plumbing | 4/29/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Gas Piping or Gas Test | 5/19/2021 | Approved | CRAIG VAUGHAN |
| Pre-Gunite | 5/19/2021 | Approved | CRAIG VAUGHAN |
| Rough-Electrical | 5/19/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Rough-Plumbing | 5/19/2021 | Approved | CRAIG VAUGHAN |
| Deck | 7/12/2021 | Approved | HAMIK HARTOUNIAN |
| Enclosure/Fence | 7/12/2021 | Approved | HAMIK HARTOUNIAN |
| Grounding or Bonding | 7/12/2021 | Approved | HAMIK HARTOUNIAN |
| Equipment Noise Level | 7/30/2021 | No Access for Inspection | RYAN TAGUINES |
| Excavation/Setback/Form/Re-Bar | 8/2/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 8/2/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/2/2021 | SGSOV Approved | HAMIK HARTOUNIAN |
| Equipment Noise Level | 8/5/2021 | Approved | RYAN TAGUINES |
| Final | 8/17/2021 | Corrections Issued | BRIAN SULLIVAN |
| Final | 8/20/2021 | OK to Issue CofO | SCOTT FINNILA |