2501 S WALNUT AVE 90291

Certificate Information: 2501 S WALNUT AVE 90291

Application / Permit
20047-10000-02034
Plan Check / Job No.
B20LA21145
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 26' X 14' POOL DEPTH MAX 4'-6" DEEP WITH 8'X9' SPA PER STANDARD POOL # 268 and ENGR DETAILS
Permit Issued
Issued on 3/2/2021
Issuing Office
Current Status
CofO Issued on 2/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2020 APPLICANT
Assigned to Plan Check Engineer 11/25/2020 FERNANDO FLORES
Corrections Issued 11/28/2020 FERNANDO FLORES
Plan Check Approved 2/26/2021 LUKE GONZALES
Issued 3/2/2021 APPLICANT
Building Plans Picked Up 3/4/2021 APPLICANT
CofO in Progress 1/19/2022 ENRIQUE MIRELES
Permit Finaled 2/1/2022 DANIEL ORRANTE
CofO Issued 2/1/2022 DANIEL ORRANTE
Permit Finaled 2/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 1/12/2021 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 1/25/2021 CECILIO NAVARRO
Work Adjacent to Public Way Cleared 1/29/2021 SAUL GARCIA
ZA Case Cleared 2/18/2021 MIGUEL GAMBOA

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-B 15021 VENTURA BLVD STE 520      SHERMAN OAKS, CA 91403
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 4/28/2021 Approved ENRIQUE MIRELES
Pre-Gunite 4/28/2021 Approved ENRIQUE MIRELES
Rough-Electrical 4/28/2021 Not Ready for Inspection ENRIQUE MIRELES
Rough-Plumbing 4/28/2021 Not Ready for Inspection ENRIQUE MIRELES
Deputy Shotcrete 5/7/2021 Approved ENRIQUE MIRELES
Deck 6/9/2021 Approved ENRIQUE MIRELES
Grounding or Bonding 6/9/2021 Approved ENRIQUE MIRELES
Enclosure/Fence 6/28/2021 Approved BRENDAN LOONEY
Equipment Noise Level 7/12/2021 Approved AGUSTIN ALVAREZMORALES
Excavation/Setback/Form/Re-Bar 8/4/2021 Approved ENRIQUE MIRELES
Final 8/4/2021 Corrections Issued ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/4/2021 SGSOV Not Ready ENRIQUE MIRELES
Final 12/28/2021 No Access for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/28/2021 SGSOV Not Ready ENRIQUE MIRELES
Final 1/19/2022 OK to Issue CofO ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 1/19/2022 SGSOV Approved ENRIQUE MIRELES