4101 W SANO ST 90065

Certificate Information: 4101 W SANO ST 90065

Application / Permit
20047-10000-02032
Plan Check / Job No.
B20LA21130
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 13'-4" X 35' POOL WITH A 7' X 7' SPA USING STANDARD DETAIL 268
Permit Issued
Issued on 2/5/2021
Issuing Office
Current Status
CofO Issued on 5/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2020 APPLICANT
Assigned to Plan Check Engineer 11/30/2020 ZAW HAN
Corrections Issued 12/2/2020 ZAW HAN
Applicant returned to address corrections 1/7/2021 LUKE GONZALES
Plan Check Approved 1/28/2021 JESSE JIMENEZ
Issued 2/5/2021 APPLICANT
CofO in Progress 4/26/2021 CRAIG VAUGHAN
Permit Finaled 5/1/2021 DEROLD HAUFF
CofO Issued 5/1/2021 DEROLD HAUFF
Permit Finaled 5/1/2021 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 12/15/2020 RICHARD REASER
Roof/Waste drainage to street Cleared 12/29/2020 CELINA MORENO
Sewer availability Cleared 12/29/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/5/2021 CELINA MORENO

Contact Information

Contractor Environmental Landscape Development Inc; Lic. No.: 902300-B 525 W WOODBURY RD      ALTADENA, CA 91001
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 2/19/2021 Approved OSVALDO PARAMO
Deputy Shotcrete 2/25/2021 Partial Approval OSVALDO PARAMO
Deck 3/9/2021 Approved OSVALDO PARAMO
Gas Piping or Gas Test 3/9/2021 Approved OSVALDO PARAMO
Enclosure/Fence 3/30/2021 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/21/2021 Approved CRAIG VAUGHAN
Final 4/21/2021 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/21/2021 SGSOV Not Ready CRAIG VAUGHAN
Final 4/23/2021 OK to Issue CofO CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/23/2021 SGSOV Approved CRAIG VAUGHAN