15004 W GREENLEAF ST 91403

Certificate Information: 15004 W GREENLEAF ST 91403

Application / Permit
20047-10000-01990
Plan Check / Job No.
B20LA20739
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED POOL AND SPA
Permit Issued
Issued on 4/8/2021
Issuing Office
Current Status
CofO Issued on 8/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2020 APPLICANT
Assigned to Plan Check Engineer 12/2/2020 RAHEL BEYENE
Corrections Issued 12/9/2020 RAHEL BEYENE
Applicant returned to address corrections 2/1/2021 GEORGE ALVAREZ
Applicant returned to address corrections 2/16/2021 TSE MING HUANG
Building Plans Picked Up 3/30/2021 APPLICANT
Applicant returned to address corrections 4/6/2021 CRYSTEL MAALOUF
Plan Check Approved 4/7/2021 CRYSTEL MAALOUF
Issued 4/8/2021 APPLICANT
CofO in Progress 12/8/2021 JACK KARGODORIAN
Permit Finaled 8/1/2022 DANIEL ORRANTE
CofO Issued 8/1/2022 DANIEL ORRANTE
Permit Finaled 8/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/24/2021 RAHEL BEYENE
Construction near power lines Cleared 3/17/2021 RIDWAN HARDY

Contact Information

Contractor C Iii C Contractors Inc; Lic. No.: 697943-B 149 SOUTH BARRINGTON AVE #158      LOS ANGELES, CA 90049
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/6/2021 Approved CHARLES POWELL
Gas Piping or Gas Test 5/6/2021 Approved CHARLES POWELL
Pool Piping 5/6/2021 Approved CHARLES POWELL
Pre-Gunite 5/6/2021 Approved CHARLES POWELL
Rough-Electrical 5/6/2021 Approved CHARLES POWELL
Deputy Shotcrete 5/17/2021 Conditional Approval DANIEL ORRANTE
Deck 10/14/2021 Corrections Issued JACK KARGODORIAN
Deck 10/27/2021 Approved JACK KARGODORIAN
Enclosure/Fence 11/18/2021 Approved JACK KARGODORIAN
Pool Equipment Noise Test 11/30/2021 Approved FELIPE PENICHE
SGSOV-Seismic Gas S/O Valve 11/30/2021 SGSOV Not Ready JACK KARGODORIAN
Final 12/6/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/6/2021 SGSOV Not Ready JENNIFER RABUCHIN
Final 12/8/2021 OK to Issue CofO JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/8/2021 SGSOV Approved JACK KARGODORIAN