10501 W KINNARD AVE 90024
Certificate Information: 10501 W KINNARD AVE 90024
- Application / Permit
- 20047-10000-01987
- Plan Check / Job No.
- B20LA20731
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL AND SPA W/ ELECTRIC COVER FOR (E) SFD, CITY OF LOS ANGELES STANDRD PLAN 268
- Permit Issued
- Issued on 9/13/2021
- Issuing Office
- Current Status
- CofO Issued on 3/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2020 | RICARDO RAMIREZ |
| Corrections Issued | 11/18/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 1/19/2021 | DANIEL YIP |
| Building Plans Picked Up | 1/19/2021 | APPLICANT |
| Applicant returned to address corrections | 8/22/2021 | AUNG SOE |
| Plan Check Approved | 8/25/2021 | AUNG SOE |
| Issued | 9/13/2021 | APPLICANT |
| CofO in Progress | 3/14/2022 | KENNETH NAGLE |
| Permit Finaled | 3/17/2022 | DANIEL ORRANTE |
| CofO Issued | 3/17/2022 | DANIEL ORRANTE |
| Permit Finaled | 3/17/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 1/19/2021 | RICARDO RAMIREZ |
| Grading Pre-Inspection | Cleared | 1/19/2021 | RICARDO RAMIREZ |
| Construction near power lines | Cleared | 8/10/2021 | TINA MIRANDA |
Contact Information
| Contractor | Coastal Aquatic Creations; Lic. No.: 697943-B | 149 SOUTH BARRINGTON AVE #158 LOS ANGELES, CA 90049 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/5/2021 | Approved | OGANES TARAKHCHYAN |
| Gas Piping or Gas Test | 10/5/2021 | Approved | OGANES TARAKHCHYAN |
| Pre-Gunite | 10/5/2021 | Approved | OGANES TARAKHCHYAN |
| Rough-Electrical | 10/5/2021 | Approved | OGANES TARAKHCHYAN |
| Rough-Plumbing | 10/5/2021 | Approved | OGANES TARAKHCHYAN |
| Deck | 12/22/2021 | Approved | OGANES TARAKHCHYAN |
| Enclosure/Fence | 1/25/2022 | Approved | OGANES TARAKHCHYAN |
| Pool Equipment Noise Test | 2/16/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Pool Equipment Noise Test | 2/17/2022 | Approved | JUSTIN CURTIS |
| Final | 2/18/2022 | Corrections Issued | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 2/18/2022 | SGSOV Approved | DEANDRE HOFFMAN |
| Final | 2/24/2022 | Partial Approval | OGANES TARAKHCHYAN |