9832 W VICAR ST 90034
Certificate Information: 9832 W VICAR ST 90034
- Application / Permit
- 20047-10000-01985
- Plan Check / Job No.
- B20LA20725
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL AND SPA FOR EXISTING SFD. 2 of 2
- Permit Issued
- Issued on 2/9/2021
- Issuing Office
- Current Status
- CofO Issued on 8/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2020 | TSE MING HUANG |
| Corrections Issued | 1/5/2021 | AUNG SOE |
| Building Plans Picked Up | 1/12/2021 | APPLICANT |
| Plan Check Approved | 2/4/2021 | FARSHAD ALIMOHAMADI |
| Issued | 2/9/2021 | APPLICANT |
| CofO in Progress | 8/14/2021 | JUAN VALENZUELA |
| Permit Finaled | 8/18/2021 | DANIEL ORRANTE |
| CofO Issued | 8/18/2021 | DANIEL ORRANTE |
| Permit Finaled | 8/18/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/11/2020 | DYLAN SITTIG |
| Grading Pre-Inspection | Cleared | 1/6/2021 | TSE MING HUANG |
Contact Information
| Contractor | C Iii C Contractors Inc; Lic. No.: 697943-C53 | 149 SOUTH BARRINGTON AVE #158 LOS ANGELES, CA 90049 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/30/2021 | Approved | EVAN COOPER |
| Gas Piping or Gas Test | 4/30/2021 | Partial Approval | EVAN COOPER |
| Pre-Gunite | 4/30/2021 | Approved | EVAN COOPER |
| Rough-Electrical | 4/30/2021 | Partial Approval | EVAN COOPER |
| Rough-Plumbing | 4/30/2021 | Partial Approval | EVAN COOPER |
| Deck | 6/22/2021 | Approved | KEVIN SARGSYAN |
| Enclosure/Fence | 7/15/2021 | Approved | KEVIN SARGSYAN |
| Pool Equipment Noise Test | 8/5/2021 | Approved | RYAN TAGUINES |
| Final | 8/6/2021 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 8/6/2021 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 8/13/2021 | OK to Issue CofO | JUAN VALENZUELA |