6923 N WISH AVE 91406

Certificate Information: 6923 N WISH AVE 91406

Application / Permit
20047-10000-01984
Plan Check / Job No.
B20LA20724
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
eplan. New swimming pool and spa per engineering design.
Permit Issued
Issued on 1/12/2021
Issuing Office
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2020 APPLICANT
Assigned to Plan Check Engineer 11/16/2020 MICHAEL LOPEZ
Corrections Issued 11/16/2020 MICHAEL LOPEZ
Applicant returned to address corrections 12/21/2020 HELEN NGUYEN
Applicant returned to address corrections 1/4/2021 HELEN NGUYEN
Plan Check Approved 1/7/2021 HELEN NGUYEN
Issued 1/12/2021 APPLICANT
CofO in Progress 3/5/2025 JON MCHUGH
No Progress 4/17/2025 SEAN WIRCH
CofO in Progress 4/17/2025 SEAN WIRCH
Permit Finaled 4/24/2025 JOHN JANSON
CofO Issued 4/24/2025 JOHN JANSON
Permit Finaled 4/24/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/8/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/8/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Raycon Corp; Lic. No.: 1038948-B 17216 SATICOY ST #402      VAN NUYS, CA 91406
Engineer Azizisefat,, Solayman; Lic. No.: C57840 19510 VENTURA BLVD STE 110      TARZANA, CA 91356

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/7/2021 Approved STEVEN BACK
Gas Piping or Gas Test 4/7/2021 Not Ready for Inspection STEVEN BACK
Grounding or Bonding 4/7/2021 Not Ready for Inspection STEVEN BACK
Pre-Gunite 4/7/2021 Approved STEVEN BACK
Pre-Inspection 4/7/2021 Partial Inspection STEVEN BACK
Rough-Electrical 4/7/2021 Partial Approval STEVEN BACK
Rough-Plumbing 4/7/2021 Corrections Issued STEVEN BACK
Deputy Shotcrete 4/9/2021 Partial Approval STEVEN BACK
Gas Piping or Gas Test 4/16/2021 Approved STEVEN BACK
Grounding or Bonding 4/16/2021 Not Ready for Inspection STEVEN BACK
Gunite 4/16/2021 Not Ready for Inspection STEVEN BACK
Rough-Electrical 4/16/2021 Approved STEVEN BACK
Rough-Plumbing 4/16/2021 Approved STEVEN BACK
Deck 5/18/2021 Approved VINCENT HANLEY
Grounding or Bonding 5/18/2021 Approved VINCENT HANLEY
Deck 5/27/2021 Approved STEVEN BACK
ELECTRICAL-Final 5/27/2021 Not Ready for Inspection STEVEN BACK
Enclosure/Fence 5/27/2021 Not Ready for Inspection STEVEN BACK
Final 5/27/2021 Not Ready for Inspection STEVEN BACK
PLUMBING-Final 5/27/2021 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 5/27/2021 SGSOV Not Ready STEVEN BACK
Enclosure/Fence 6/1/2021 Conditional Approval STEVEN BACK
Final 6/1/2021 Corrections Issued STEVEN BACK
Final 10/29/2024 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 10/29/2024 SGSOV Approved JON MCHUGH
Special/Order Compliance 11/12/2024 Not Ready for Inspection JON MCHUGH
Equipment Noise Level 3/3/2025 Approved FELIPE PENICHE
Final 3/5/2025 OK to Issue CofO JON MCHUGH
Enclosure/Fence 3/13/2025 Approved JON MCHUGH