2025 S CAMDEN AVE 90025

Certificate Information: 2025 S CAMDEN AVE 90025

Application / Permit
20047-10000-01979
Plan Check / Job No.
B20LA20677
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
Eplan. New swimming pool and spa per City of Los Angeles Standard Plan # 268 and engineering details.
Permit Issued
Issued on 1/15/2021
Issuing Office
Current Status
CofO Issued on 10/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 HELEN NGUYEN
Corrections Issued 11/12/2020 HELEN NGUYEN
Applicant returned to address corrections 1/6/2021 HELEN NGUYEN
Applicant returned to address corrections 1/12/2021 HELEN NGUYEN
Plan Check Approved 1/14/2021 HELEN NGUYEN
Issued 1/15/2021 APPLICANT
CofO in Progress 10/29/2021 KENNETH NAGLE
Permit Finaled 10/29/2021 KENNETH NAGLE
CofO Issued 10/29/2021 KENNETH NAGLE
Permit Finaled 10/29/2021 KENNETH NAGLE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/6/2021 HELEN NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/12/2021 Partial Approval OGANES TARAKHCHYAN
Gas Piping or Gas Test 4/21/2021 Approved KEVIN SARGSYAN
Pre-Gunite 4/21/2021 Conditional Approval KEVIN SARGSYAN
Rough-Electrical 4/21/2021 Approved KEVIN SARGSYAN
Rough-Plumbing 4/21/2021 Approved KEVIN SARGSYAN
Deck 5/21/2021 Approved OGANES TARAKHCHYAN
Grounding or Bonding 5/21/2021 Approved OGANES TARAKHCHYAN
Deck 6/24/2021 Approved OGANES TARAKHCHYAN
Enclosure/Fence 6/24/2021 Approved OGANES TARAKHCHYAN
Grounding or Bonding 6/24/2021 Approved OGANES TARAKHCHYAN
Equipment Noise Level 8/12/2021 Approved RYAN TAGUINES
Excavation/Setback/Form/Re-Bar 8/18/2021 Approved OGANES TARAKHCHYAN
Final 8/18/2021 Partial Approval OGANES TARAKHCHYAN
Pre-Gunite 8/18/2021 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/18/2021 SGSOV Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 10/21/2021 Approved OGANES TARAKHCHYAN
Final 10/21/2021 Partial Approval OGANES TARAKHCHYAN