2025 S CAMDEN AVE 90025
Certificate Information: 2025 S CAMDEN AVE 90025
- Application / Permit
- 20047-10000-01979
- Plan Check / Job No.
- B20LA20677
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Eplan. New swimming pool and spa per City of Los Angeles Standard Plan # 268 and engineering details.
- Permit Issued
- Issued on 1/15/2021
- Issuing Office
- Current Status
- CofO Issued on 10/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | HELEN NGUYEN |
| Corrections Issued | 11/12/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 1/6/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 1/12/2021 | HELEN NGUYEN |
| Plan Check Approved | 1/14/2021 | HELEN NGUYEN |
| Issued | 1/15/2021 | APPLICANT |
| CofO in Progress | 10/29/2021 | KENNETH NAGLE |
| Permit Finaled | 10/29/2021 | KENNETH NAGLE |
| CofO Issued | 10/29/2021 | KENNETH NAGLE |
| Permit Finaled | 10/29/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/6/2021 | HELEN NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/12/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Gas Piping or Gas Test | 4/21/2021 | Approved | KEVIN SARGSYAN |
| Pre-Gunite | 4/21/2021 | Conditional Approval | KEVIN SARGSYAN |
| Rough-Electrical | 4/21/2021 | Approved | KEVIN SARGSYAN |
| Rough-Plumbing | 4/21/2021 | Approved | KEVIN SARGSYAN |
| Deck | 5/21/2021 | Approved | OGANES TARAKHCHYAN |
| Grounding or Bonding | 5/21/2021 | Approved | OGANES TARAKHCHYAN |
| Deck | 6/24/2021 | Approved | OGANES TARAKHCHYAN |
| Enclosure/Fence | 6/24/2021 | Approved | OGANES TARAKHCHYAN |
| Grounding or Bonding | 6/24/2021 | Approved | OGANES TARAKHCHYAN |
| Equipment Noise Level | 8/12/2021 | Approved | RYAN TAGUINES |
| Excavation/Setback/Form/Re-Bar | 8/18/2021 | Approved | OGANES TARAKHCHYAN |
| Final | 8/18/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Pre-Gunite | 8/18/2021 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2021 | SGSOV Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 10/21/2021 | Approved | OGANES TARAKHCHYAN |
| Final | 10/21/2021 | Partial Approval | OGANES TARAKHCHYAN |