6181 W TEMPLE HILL DR 90068

Certificate Information: 6181 W TEMPLE HILL DR 90068

Application / Permit
20047-10000-01907
Plan Check / Job No.
B20LA19174
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED EXTERIOR SWIMMING POOL 10.5' X 27'
Permit Issued
Issued on 10/20/2021
Issuing Office
Metro
Current Status
Permit Closed on 3/28/2024
Certificate of Occupancy
Permit Closed More Information

Permit Application Status History

Submitted 10/16/2020 APPLICANT
Assigned to Plan Check Engineer 10/25/2020 ARMEN JIVALAGIAN
Corrections Issued 10/27/2020 ARMEN JIVALAGIAN
Quality Review Completed 10/29/2020 CHAD DOI
Applicant returned to address corrections 6/3/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 9/9/2021 ARMEN JIVALAGIAN
Plan Check Approved 10/8/2021 ARMEN JIVALAGIAN
Issued 10/20/2021 APPLICANT
Building Plans Picked Up 10/21/2021 APPLICANT
Permit Closed 3/28/2024 BRIAN SULLIVAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/10/2021 CECILIO NAVARRO
Low Impact Development Cleared 3/23/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 4/13/2021 CECILIO NAVARRO
Sewer availability Cleared 4/28/2021 CECILIO NAVARRO
Grading Pre-Inspection Cleared 10/8/2021 ARMEN JIVALAGIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Nohroodi,, Nader Gholi; Lic. No.: C36971 7389 PERIGORD CT      TUJUNGA, CA 91042
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool/Spa Cover 11/15/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Pre-Inspection 11/15/2021 Approved CHRIS CHRISTENSEN
Rough-Electrical 11/15/2021 Conditional Approval CHRIS CHRISTENSEN
Rough-Plumbing 11/15/2021 Conditional Approval CHRIS CHRISTENSEN
Special/Order Compliance 11/30/2021 Corrections Issued BRIAN SULLIVAN
Special/Order Compliance 12/23/2021 Corrections Issued RUBEN SALAS
Excavation/Setback/Form/Re-Bar 1/18/2022 Not Ready for Inspection BRIAN SULLIVAN
Special/Order Compliance 1/18/2022 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/7/2022 Not Ready for Inspection BRIAN SULLIVAN
Special/Order Compliance 2/7/2022 Not Ready for Inspection RUBEN SALAS
Special/Order Compliance 9/22/2022 Corrections Issued BRIAN SULLIVAN
Special/Order Compliance 9/23/2022 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 3/28/2024 Not Ready for Inspection BRIAN SULLIVAN
Final 3/28/2024 Permit Closed BRIAN SULLIVAN
Pre-Gunite 3/28/2024 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 3/28/2024 SGSOV Not Ready BRIAN SULLIVAN