2598 N THAMES PL 90046

Certificate Information: 2598 N THAMES PL 90046

Application / Permit
20047-10000-01871
Plan Check / Job No.
B20LA19693
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL
Permit Issued
Issued on 2/25/2021
Issuing Office
Current Status
CofO Issued on 2/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2020 APPLICANT
Assigned to Plan Check Engineer 10/31/2020 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 11/17/2020 APPLICANT
Corrections Issued 11/18/2020 TEODORO DIAZ RODRIGUEZ
Quality Review Completed 11/19/2020 EUGENE BARBEAU
Plan Check Approved 2/25/2021 TEODORO DIAZ RODRIGUEZ
Issued 2/25/2021 APPLICANT
CofO in Progress 2/18/2026 ROY SPAULDING
Permit Finaled 2/22/2026 DEROLD HAUFF
CofO Issued 2/22/2026 DEROLD HAUFF
Permit Finaled 2/22/2026 DEROLD HAUFF

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/17/2022 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 3/17/2022 Corrections Issued RAUL BARAJAS
Pre-Gunite 6/24/2024 Corrections Issued RAUL BARAJAS
Pool Piping 8/13/2024 Not Ready for Inspection RAUL BARAJAS
Pre-Gunite 8/13/2024 Not Ready for Inspection RAUL BARAJAS
Rough-Plumbing 8/13/2024 Not Ready for Inspection RAUL BARAJAS
Pool Piping 8/15/2024 Not Ready for Inspection BRIAN SULLIVAN
Pre-Gunite 8/15/2024 Not Ready for Inspection BRIAN SULLIVAN
Rough-Plumbing 8/15/2024 Not Ready for Inspection BRIAN SULLIVAN
Pool Piping 8/27/2024 Approved RAUL BARAJAS
Pre-Gunite 8/27/2024 Approved RAUL BARAJAS
Rough-Plumbing 8/27/2024 Approved RAUL BARAJAS
Deputy Shotcrete 10/10/2024 Conditional Approval RAUL BARAJAS
Enclosure/Fence 7/23/2025 Corrections Issued ROY SPAULDING
Enclosure/Fence 7/29/2025 Approved ROY SPAULDING
Final 8/25/2025 Corrections Issued ROY SPAULDING
Final 11/21/2025 Not Ready for Inspection ROY SPAULDING
Final 2/18/2026 OK to Issue CofO ROY SPAULDING