4100 N CAMELLIA AVE 91604
Certificate Information: 4100 N CAMELLIA AVE 91604
- Application / Permit
- 20047-10000-01865
- Plan Check / Job No.
- B20LA19641
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ATTENTION CARLOS Eplan. New swimming pool and spa per City of Los Angeles Standard Plan # 268.
- Permit Issued
- Issued on 4/20/2021
- Issuing Office
- Current Status
- CofO Issued on 11/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2020 | HELEN NGUYEN |
| Corrections Issued | 11/2/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 3/4/2021 | CARLOS MONTES |
| Plan Check Approved | 3/31/2021 | LARRY LEE |
| Issued | 4/20/2021 | APPLICANT |
| CofO in Progress | 11/2/2021 | MICHAEL PELHAM |
| Permit Finaled | 11/3/2021 | MICHAEL SMITH |
| CofO Issued | 11/3/2021 | MICHAEL SMITH |
| Permit Finaled | 11/3/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/23/2021 | TINA MIRANDA |
Contact Information
| Contractor | Pool Icons Inc; Lic. No.: 479446-C53 | 15935 DEL PRADO DR HACIENDA HEIGHTS, CA 91745 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/14/2021 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 5/14/2021 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 5/14/2021 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 5/14/2021 | Approved | ARAM AVEDISIAN |
| Rough-Plumbing | 5/14/2021 | Approved | ARAM AVEDISIAN |
| Deck | 6/28/2021 | Corrections Issued | THOMAS FINNILA |
| Enclosure/Fence | 6/28/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Deck | 8/16/2021 | Partial Inspection | MICHEL ABAJAN |
| Enclosure/Fence | 8/16/2021 | Approved | MICHEL ABAJAN |
| Final | 8/16/2021 | Partial Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 8/16/2021 | SGSOV Approved | MICHEL ABAJAN |
| Equipment Noise Level | 9/1/2021 | Approved | FELIPE PENICHE |
| Final | 9/24/2021 | No Access for Inspection | THOMAS FINNILA |
| Pre-Inspection | 9/27/2021 | Corrections Issued | THOMAS FINNILA |
| Final | 10/22/2021 | Corrections Issued | THOMAS FINNILA |
| Final | 11/2/2021 | OK to Issue CofO | MICHAEL PELHAM |