12354 W HUSTON ST 91607

Certificate Information: 12354 W HUSTON ST 91607

Application / Permit
20047-10000-01857
Plan Check / Job No.
B20LA19561
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 14' X 30' POOL W/ 8' X 8' SPA PER STANDARD PLAN #268
Permit Issued
Issued on 1/13/2021
Issuing Office
Current Status
CofO Issued on 10/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2020 APPLICANT
Assigned to Plan Check Engineer 12/26/2020 RICARDO RAMIREZ
Corrections Issued 12/26/2020 RICARDO RAMIREZ
Building Plans Picked Up 12/28/2020 APPLICANT
Issued 1/13/2021 APPLICANT
CofO in Progress 10/22/2021 CHRISTOPHE COCHRAN
CofO in Progress 10/22/2021 CHRISTOPHE COCHRAN
Permit Finaled 10/26/2021 MICHAEL SMITH
CofO Issued 10/26/2021 MICHAEL SMITH
Permit Finaled 10/26/2021 MICHAEL SMITH

Permit Application Clearance Information

Miscellaneous Cleared 12/29/2020 MIGUEL GAMBOA
Miscellaneous Cleared 12/29/2020 MIGUEL GAMBOA
Specific Plan Cleared 12/29/2020 MIGUEL GAMBOA
ZI Cleared 12/29/2020 MIGUEL GAMBOA
Construction near power lines Cleared 1/12/2021 OSCAR CASTRO

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-B 15021 VENTURA BLVD STE 520      SHERMAN OAKS, CA 91403
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 4/20/2021 Approved RICHARD DOCKUS
Pre-Gunite 4/20/2021 Approved RICHARD DOCKUS
Rough-Electrical 4/20/2021 Approved RICHARD DOCKUS
Rough-Plumbing 4/20/2021 Approved RICHARD DOCKUS
Deputy Shotcrete 4/21/2021 Conditional Approval DANIEL ORRANTE
Deck 7/29/2021 Approved CHRISTOPHE COCHRAN
Grounding or Bonding 7/29/2021 Approved CHRISTOPHE COCHRAN
Enclosure/Fence 9/14/2021 Corrections Issued CHRISTOPHE COCHRAN
Enclosure/Fence 9/16/2021 Approved ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 10/12/2021 Approved ARAM AVEDISIAN
Final 10/12/2021 Corrections Issued ARAM AVEDISIAN
Pool Equipment Noise Test 10/12/2021 Approved FELIPE PENICHE
SGSOV-Seismic Gas S/O Valve 10/12/2021 SGSOV Approved ARAM AVEDISIAN
Final 10/18/2021 OK to Issue CofO CHRISTOPHE COCHRAN