712 S HOLMBY AVE 90024
Certificate Information: 712 S HOLMBY AVE 90024
- Application / Permit
- 20047-10000-01839
- Plan Check / Job No.
- B20LA19328
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL WITH AUTOMATED POOL COVER, NEW SPA PER STD PLAN #268
- Permit Issued
- Issued on 1/20/2022
- Issuing Office
- Current Status
- CofO Issued on 8/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 1/14/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 1/21/2021 | TIEN JEN WANG |
| Building Plans Picked Up | 1/26/2021 | APPLICANT |
| Applicant returned to address corrections | 2/26/2021 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 3/4/2021 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 12/15/2021 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 1/20/2022 | MAHNAZ NOURHASHEMI |
| Issued | 1/20/2022 | APPLICANT |
| CofO in Progress | 8/21/2025 | DANIEL VERA |
| CofO in Progress | 8/26/2025 | DANIEL VERA |
| CofO in Progress | 8/26/2025 | DANIEL VERA |
| Permit Finaled | 8/27/2025 | RICHARD STEINBACH |
| CofO Issued | 8/27/2025 | RICHARD STEINBACH |
| Permit Finaled | 8/27/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/15/2021 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Intex Design And Construction Inc; Lic. No.: 981718-B | 15021 VENTURA BLVD STE 520 SHERMAN OAKS, CA 91403 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 4/25/2022 | Corrections Issued | BRENDAN LOONEY |
| Pre-Gunite | 4/28/2022 | Corrections Issued | BRENDAN LOONEY |
| Pre-Gunite | 6/28/2022 | Corrections Issued | BRENDAN LOONEY |
| Pre-Gunite | 9/20/2022 | Corrections Issued | STEPHANIE SWANSON |
| Special/Order Compliance | 9/20/2022 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Gunite | 10/7/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Deck | 10/7/2024 | Corrections Issued | STEPHANIE SWANSON |
| Grounding or Bonding | 10/7/2024 | Partial Approval | STEPHANIE SWANSON |
| Special/Order Compliance | 4/15/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Enclosure/Fence | 5/21/2025 | Approved | SEAN HAUPT |
| Final | 5/21/2025 | Corrections Issued | SEAN HAUPT |
| Pool Equipment Noise Test | 7/3/2025 | Approved | ROBERT CHAVEZ |
| Final | 7/15/2025 | Corrections Issued | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 7/15/2025 | SGSOV Not Ready | DANIEL VERA |
| Final | 7/23/2025 | Corrections Issued | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 7/23/2025 | SGSOV Approved | DANIEL VERA |
| ELECTRICAL-Final | 7/31/2025 | Approved | DANIEL VERA |
| Final | 7/31/2025 | Not Ready for Inspection | DANIEL VERA |
| Final | 8/13/2025 | Not Ready for Inspection | DANIEL VERA |
| Final | 8/20/2025 | OK to Issue CofO | DANIEL VERA |