9640 N STANWIN AVE 91331

Certificate Information: 9640 N STANWIN AVE 91331

Application / Permit
20047-10000-01791
Plan Check / Job No.
B20LA18988
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL (17' X 32') PER STANDARD PLAN #268
Permit Issued
Issued on 4/30/2021
Issuing Office
Current Status
CofO Issued on 1/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2020 APPLICANT
Assigned to Plan Check Engineer 10/23/2020 FARSHAD ALIMOHAMADI
Corrections Issued 10/26/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 3/3/2021 LUISANGEL VALENZUELA
Applicant returned to address corrections 4/22/2021 JEFFREY TANGONAN
Issued 4/30/2021 APPLICANT
Building Plans Picked Up 6/4/2021 APPLICANT
CofO in Progress 12/23/2021 MICHEL ABAJAN
Permit Finaled 1/19/2022 MICHAEL SMITH
CofO Issued 1/19/2022 MICHAEL SMITH
Permit Finaled 1/19/2022 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Premier Pool Plastering; Lic. No.: 625132-C53 14520 FOOTHILL BLVD      SYLMAR, CA 91342

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 6/23/2021 Corrections Issued MICHEL ABAJAN
Pre-Gunite 7/1/2021 Approved MICHEL ABAJAN
Deck 7/26/2021 Approved CHRISTOPHER DELLEFIELD
Enclosure/Fence 8/19/2021 Corrections Issued MICHEL ABAJAN
Enclosure/Fence 8/23/2021 Approved MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 9/27/2021 Approved MICHEL ABAJAN
Final 9/27/2021 OK to Issue CofO MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/27/2021 SGSOV Approved MICHEL ABAJAN
Equipment Noise Level 9/29/2021 Approved FELIPE PENICHE