6731 N RUBIO AVE 91406

Certificate Information: 6731 N RUBIO AVE 91406

Application / Permit
20047-10000-01737
Plan Check / Job No.
B20LA18508
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA PER STANDARD PLAN 268
Permit Issued
Issued on 1/15/2021
Issuing Office
Current Status
CofO Issued on 9/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2020 APPLICANT
Assigned to Plan Check Engineer 10/13/2020 ADAM HEGAZI
Corrections Issued 10/14/2020 ADAM HEGAZI
Applicant returned to address corrections 11/20/2020 RARES BODEA
Plan Check Approved 1/11/2021 RICARDO RAMIREZ
Issued 1/15/2021 APPLICANT
Building Plans Picked Up 1/20/2021 APPLICANT
CofO in Progress 7/8/2021 JACK KARGODORIAN
CofO in Progress 7/8/2021 JACK KARGODORIAN
Permit Finaled 9/25/2021 MICHAEL SMITH
CofO Issued 9/25/2021 MICHAEL SMITH
Permit Finaled 9/25/2021 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 1/5/2021 WALTER RAMIREZ
Construction within easement Cleared 1/5/2021 WALTER RAMIREZ

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-B 15021 VENTURA BLVD STE 520      SHERMAN OAKS, CA 91403
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 4/23/2021 Corrections Issued ARTHUR SARGSYAN
Pre-Gunite 4/23/2021 Not Ready for Inspection ARTHUR SARGSYAN
Rough-Electrical 4/23/2021 Not Ready for Inspection ARTHUR SARGSYAN
Rough-Plumbing 4/23/2021 Not Ready for Inspection ARTHUR SARGSYAN
Gas Piping or Gas Test 5/4/2021 No Access for Inspection ARTHUR SARGSYAN
Rough-Electrical 5/4/2021 No Access for Inspection ARTHUR SARGSYAN
Rough-Plumbing 5/4/2021 No Access for Inspection ARTHUR SARGSYAN
Gas Piping or Gas Test 5/11/2021 Approved ARTHUR SARGSYAN
Pre-Gunite 5/11/2021 Approved ARTHUR SARGSYAN
Rough-Electrical 5/11/2021 Approved ARTHUR SARGSYAN
Rough-Plumbing 5/11/2021 Approved ARTHUR SARGSYAN
Gas Piping or Gas Test 5/14/2021 Approved ARTHUR SARGSYAN
Rough-Electrical 5/14/2021 Approved ARTHUR SARGSYAN
Rough-Plumbing 5/14/2021 Approved ARTHUR SARGSYAN
Deck 5/27/2021 Approved ARTHUR SARGSYAN
Grounding or Bonding 5/27/2021 Approved ARTHUR SARGSYAN
Deck 6/4/2021 Approved MATTHEW NELSON
Grounding or Bonding 6/4/2021 Approved MATTHEW NELSON
Enclosure/Fence 6/10/2021 Approved ARTHUR SARGSYAN
Equipment Noise Level 6/21/2021 Approved FELIPE PENICHE
Excavation/Setback/Form/Re-Bar 6/23/2021 Approved JACK KARGODORIAN
Final 6/23/2021 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 6/23/2021 SGSOV Approved JACK KARGODORIAN
Final 6/29/2021 Not Ready for Inspection JACK KARGODORIAN
Final 7/8/2021 OK to Issue CofO JACK KARGODORIAN