7441 W 90TH ST 90045
Certificate Information: 7441 W 90TH ST 90045
- Application / Permit
- 20047-10000-01667
- Plan Check / Job No.
- B20LA17809
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New 23' x 15' Pool With 6'x10' Spa Per LA City Standard plan# 265
- Permit Issued
- Issued on 8/2/2021
- Issuing Office
- Current Status
- CofO Issued on 8/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | AMIR DANAI |
| Corrections Issued | 10/2/2020 | AMIR DANAI |
| Applicant returned to address corrections | 1/7/2021 | SINA KHOSRAVI |
| Plan Check Approved | 5/20/2021 | SINA KHOSRAVI |
| Issued | 8/2/2021 | APPLICANT |
| Building Plans Picked Up | 8/4/2021 | APPLICANT |
| CofO in Progress | 7/26/2022 | BOBBY KEY |
| Permit Finaled | 8/2/2022 | DANIEL ORRANTE |
| CofO Issued | 8/2/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/2/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/19/2020 | BRIAN MILLER |
| GPI Written Notices | Cleared | 1/7/2021 | AMIR DANAI |
| Construction near power lines | Cleared | 4/27/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Way To Go Builders; Lic. No.: 1043721-B | 6700 FALLBROOK AVE STE 133 WEST HILLS, CA 91307 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/14/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Pre-Gunite | 10/13/2021 | Corrections Issued | KENNETH NAGLE |
| Rough-Plumbing | 10/13/2021 | Partial Approval | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 1/31/2022 | Approved | BOBBY KEY |
| Grounding or Bonding | 1/31/2022 | Partial Approval | BOBBY KEY |
| Pool Piping | 1/31/2022 | Approved | BOBBY KEY |
| Pre-Gunite | 1/31/2022 | Approved | BOBBY KEY |
| Enclosure/Fence | 6/2/2022 | Corrections Issued | BOBBY KEY |
| Grounding or Bonding | 6/2/2022 | Corrections Issued | BOBBY KEY |
| Pool Equipment Noise Test | 6/6/2022 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| Enclosure/Fence | 6/8/2022 | Corrections Issued | BOBBY KEY |
| Grounding or Bonding | 6/8/2022 | Approved | BOBBY KEY |
| Enclosure/Fence | 6/28/2022 | Approved | BOBBY KEY |
| Equipment Noise Level | 6/30/2022 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| Pool Equipment Noise Test | 7/7/2022 | Not Ready for Inspection | JAMES VORHIS |
| Equipment Noise Level | 7/11/2022 | Approved | JAMES VORHIS |
| Final | 7/18/2022 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/18/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Final | 7/26/2022 | OK to Issue CofO | BOBBY KEY |