16381 W SLOAN DR 90049

Certificate Information: 16381 W SLOAN DR 90049

Application / Permit
20047-10000-01365
Plan Check / Job No.
B20LA15382
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED 13' X 25' POOL AND SPA PER L.A. CITY STANDARD PLAN #270 ALONG NORTHERLY LOT LINE.
Permit Issued
Issued on 10/20/2020
Issuing Office
Current Status
CofO Issued on 5/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2020 APPLICANT
Assigned to Plan Check Engineer 8/29/2020 LAWRENCE QUIRANTE
Corrections Issued 8/29/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/21/2020 JESSE JIMENEZ
Building Plans Picked Up 9/22/2020 APPLICANT
Applicant returned to address corrections 9/29/2020 SAMUEL GONZALEZ
Applicant returned to address corrections 10/7/2020 FERNANDO FLORES
Plan Check Approved 10/9/2020 FERNANDO FLORES
Issued 10/20/2020 APPLICANT
CofO in Progress 5/18/2021 CHRISTOPHER WILSON
Permit Finaled 5/18/2021 VINCENT COTTON
CofO Issued 5/18/2021 VINCENT COTTON
Permit Finaled 5/18/2021 VINCENT COTTON

Permit Application Clearance Information

Specific Plan Cleared 9/1/2020 SARAHI ORTEGA
Grading Pre-Inspection Cleared 9/29/2020 LAWRENCE QUIRANTE

Contact Information

Contractor Owner-Builder       ,
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/9/2020 Not Ready for Inspection CARLOS MATAMOROS
Pool Piping 12/9/2020 Not Ready for Inspection CARLOS MATAMOROS
Pre-Gunite 12/9/2020 Corrections Issued CARLOS MATAMOROS
Grounding or Bonding 1/8/2021 Not Ready for Inspection CARLOS MATAMOROS
Pre-Gunite 1/8/2021 Not Ready for Inspection CARLOS MATAMOROS
Rough-Electrical 1/8/2021 Not Ready for Inspection CARLOS MATAMOROS
Rough-Plumbing 1/8/2021 Not Ready for Inspection CARLOS MATAMOROS
Grounding or Bonding 1/12/2021 Approved CARLOS MATAMOROS
Pool Piping 1/12/2021 Approved CARLOS MATAMOROS
Special/Order Compliance 1/12/2021 Approved CARLOS MATAMOROS
Gas Piping or Gas Test 1/25/2021 Approved CARLOS MATAMOROS
Enclosure/Fence 3/8/2021 Approved ANTHONY MCDOWALL
Pool Equipment Noise Test 5/12/2021 Approved ALFREDO FLORES
ELECTRICAL-Final 5/13/2021 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/13/2021 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 5/13/2021 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Gunite 5/13/2021 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 5/13/2021 SGSOV Approved CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/14/2021 Approved CHRISTOPHER WILSON
Final 5/14/2021 Conditional Approval CHRISTOPHER WILSON