8812 N SNOWDEN AVE 91331
Certificate Information: 8812 N SNOWDEN AVE 91331
- Application / Permit
- 20047-10000-01277
- Plan Check / Job No.
- B20LA14666
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Eplan. New swimming pool per city of Los Angeles standard plan # 268.
- Permit Issued
- Issued on 12/30/2020
- Issuing Office
- Current Status
- CofO Issued on 5/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2020 | MONICA RAMIREZ |
| Corrections Issued | 8/17/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 12/3/2020 | HELEN NGUYEN |
| Plan Check Approved | 12/22/2020 | HELEN NGUYEN |
| Issued | 12/30/2020 | APPLICANT |
| CofO in Progress | 3/11/2021 | GREGG CUMMINGS |
| CofO Issued | 5/22/2021 | MICHAEL SMITH |
| Permit Finaled | 5/22/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/2/2020 | ERNEST FRESQUEZ |
Contact Information
| Contractor | Ultimate Green Construction Inc; Lic. No.: 1023605-B | 13302 FILMORE ST PACOIMA, CA 91331 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1499 IRIS GROVE DR CORONA, CA 92881 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/12/2021 | Approved | GREGG CUMMINGS |
| Rough-Electrical | 1/12/2021 | Approved | GREGG CUMMINGS |
| Rough-Plumbing | 1/12/2021 | Approved | GREGG CUMMINGS |
| Deck | 2/4/2021 | Approved | GREGG CUMMINGS |
| Enclosure/Fence | 2/4/2021 | Approved | GREGG CUMMINGS |
| Grounding or Bonding | 2/4/2021 | Approved | GREGG CUMMINGS |
| Final | 2/19/2021 | Corrections Issued | GREGG CUMMINGS |
| Pre-Gunite | 2/19/2021 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/19/2021 | SGSOV Not Ready | GREGG CUMMINGS |
| Pool Equipment Noise Test | 2/24/2021 | Approved | FELIPE PENICHE |
| ELECTRICAL-Final | 3/8/2021 | Approved | GREGG CUMMINGS |
| Final | 3/8/2021 | OK to Issue CofO | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/8/2021 | SGSOV Approved | GREGG CUMMINGS |