4618 N ARCOLA AVE 91602
Certificate Information: 4618 N ARCOLA AVE 91602
- Application / Permit
- 20047-10000-01250
- Plan Check / Job No.
- B20LA14218
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Eplan. New swimming pool per City of Los Angeles Standard Plan #268.
- Permit Issued
- Issued on 12/29/2020
- Issuing Office
- Current Status
- CofO Issued on 6/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2020 | MONICA RAMIREZ |
| Corrections Issued | 8/11/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 10/12/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 10/20/2020 | HELEN NGUYEN |
| Plan Check Approved | 12/23/2020 | HELEN NGUYEN |
| Issued | 12/29/2020 | APPLICANT |
| CofO in Progress | 3/31/2022 | MATTHEW NELSON |
| CofO in Progress | 3/31/2022 | MATTHEW NELSON |
| Permit Finaled | 6/11/2022 | DANIEL ORRANTE |
| CofO Issued | 6/11/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/11/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/6/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Symphony Pools Inc; Lic. No.: 466383-C53 | 4685 RUNWAY STREET UNIT P SIMI VALLEY, CA 93063 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/1/2021 | Approved | DANIEL DREW |
| Gas Piping or Gas Test | 2/1/2021 | Approved | DANIEL DREW |
| Grounding or Bonding | 2/1/2021 | Approved | DANIEL DREW |
| Pool Piping | 2/1/2021 | Approved | DANIEL DREW |
| Pre-Gunite | 2/1/2021 | Approved | DANIEL DREW |
| Pool Piping | 2/11/2021 | Partial Approval | DANIEL DREW |
| Rough-Electrical | 2/11/2021 | Partial Approval | DANIEL DREW |
| Rough-Plumbing | 2/11/2021 | Partial Approval | DANIEL DREW |
| Enclosure/Fence | 4/14/2021 | Approved | DANIEL DREW |
| Pool Equipment Noise Test | 4/23/2021 | Approved | ROBERT CHAVEZ |
| ELECTRICAL-Final | 5/13/2021 | Approved | MATTHEW NELSON |
| Final | 5/13/2021 | Partial Approval | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/13/2021 | SGSOV Approved | MATTHEW NELSON |
| Final | 3/31/2022 | OK to Issue CofO | MATTHEW NELSON |