1990 N GLENCOE WAY 90068
Certificate Information: 1990 N GLENCOE WAY 90068
- Application / Permit
- 20047-10000-01180
- Plan Check / Job No.
- B20LA13525
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW RAISED SWIMMING POOL PER ENGINEER DESIGN
- Permit Issued
- Issued on 4/5/2021
- Issuing Office
- Current Status
- CofO Issued on 2/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2020 | ZAW HAN |
| Corrections Issued | 8/12/2020 | ZAW HAN |
| Quality Review Completed | 9/9/2020 | TU HUA |
| Building Plans Picked Up | 9/14/2020 | APPLICANT |
| Plan Check Approved | 1/21/2021 | ZAW HAN |
| Issued | 4/5/2021 | APPLICANT |
| CofO in Progress | 1/26/2024 | BRIAN SULLIVAN |
| Permit Finaled | 2/19/2024 | DEROLD HAUFF |
| CofO Issued | 2/19/2024 | DEROLD HAUFF |
| Permit Finaled | 2/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/2/2020 | WALLIE JONG |
| Sewer availability | Cleared | 9/2/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2020 | WALLIE JONG |
| Excavation more than 5-ft deep | Cleared | 1/7/2021 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 1/21/2021 | VASIL MIHALEV |
Contact Information
| Contractor | Ridge Inc; Lic. No.: 934983-B | 4541 FORMAN AVE TOLUCA LAKE, CA 91602 |
| Engineer | Cai,, Luo B; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 4/15/2021 | Partial Approval | JOSEPH MCGARRY |
| Pre-Inspection | 4/19/2021 | Partial Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 5/18/2021 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/7/2021 | Corrections Issued | BRIAN SULLIVAN |
| Deputy Shotcrete | 4/27/2022 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/23/2022 | Corrections Issued | BRIAN SULLIVAN |
| Pre-Gunite | 8/16/2022 | Corrections Issued | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 4/17/2023 | Approved | BRIAN SULLIVAN |
| Final | 4/17/2023 | No Access for Inspection | BRIAN SULLIVAN |
| Pre-Gunite | 4/17/2023 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/17/2023 | SGSOV Not Ready | BRIAN SULLIVAN |
| Final | 11/21/2023 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | RAUL BARAJAS |
| Final | 1/25/2024 | OK to Issue CofO | BRIAN SULLIVAN |