5703 N CEDROS AVE 91411
Certificate Information: 5703 N CEDROS AVE 91411
- Application / Permit
- 20047-10000-01125
- Plan Check / Job No.
- B20LA12956
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL & SPA (14x26) STANDARD PLAN #270
- Permit Issued
- Issued on 9/21/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2020 | TSE MING HUANG |
| Corrections Issued | 7/30/2020 | TSE MING HUANG |
| Plan Check Approved | 9/11/2020 | AMIR DANAI |
| Issued | 9/21/2020 | APPLICANT |
| Building Plans Picked Up | 9/22/2020 | APPLICANT |
| CofO in Progress | 3/9/2021 | JENNIFER RABUCHIN |
| No Progress | 3/13/2021 | MICHAEL TEMPLE |
| CofO in Progress | 3/13/2021 | MICHAEL TEMPLE |
| CofO in Progress | 3/13/2021 | MICHAEL TEMPLE |
| CofO Issued | 4/10/2021 | MICHAEL SMITH |
| Permit Finaled | 4/10/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Royal Moon Pools Inc; Lic. No.: 1041907-C53 | 2518 SAN MACHID WAY ROSAMOND, CA 93560 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 9/24/2020 | Approved | WILLIAM KUEHN |
| Deputy Shotcrete | 10/1/2020 | Conditional Approval | WILLIAM KUEHN |
| Deck | 10/13/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Deck | 11/19/2020 | Approved | MICHEL ABAJAN |
| Enclosure/Fence | 12/18/2020 | Corrections Issued | MARK JOHNSON |
| Enclosure/Fence | 1/11/2021 | Corrections Issued | JOHN HAYES |
| Enclosure/Fence | 1/15/2021 | Not Ready for Inspection | JOHN HAYES |
| Special/Order Compliance | 1/15/2021 | Not Ready for Inspection | JOHN HAYES |
| Enclosure/Fence | 1/25/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Enclosure/Fence | 2/1/2021 | Not Ready for Inspection | JOHN HAYES |
| Enclosure/Fence | 2/5/2021 | Approved | DAVID SCANTLIN |
| Enclosure/Fence | 2/9/2021 | Partial Inspection | MICHEL ABAJAN |
| Equipment Noise Level | 3/1/2021 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 3/2/2021 | Approved | JENNIFER RABUCHIN |
| Final | 3/2/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/2/2021 | SGSOV Approved | JENNIFER RABUCHIN |