2437 S PATRICIA AVE 90064

Certificate Information: 2437 S PATRICIA AVE 90064

Application / Permit
20047-10000-01095
Plan Check / Job No.
B20LA12499
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 16'W X 25'L X 5.5'D SWIMMING POOL WITH 9'W X 8'L X 3'D SPA. SWIMMING POOL & SPA PER LA CITY STANDARD PLAN # 254.
Permit Issued
Issued on 1/12/2021
Issuing Office
Current Status
CofO Issued on 9/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2020 APPLICANT
Assigned to Plan Check Engineer 8/6/2020 CHUNG-WEN CHUANG
Corrections Issued 8/18/2020 CHUNG-WEN CHUANG
Quality Review Completed 8/26/2020 KESETE HAREGOT
Plan Check Approved 1/7/2021 CHUNG-WEN CHUANG
Issued 1/12/2021 APPLICANT
Building Plans Picked Up 1/13/2021 APPLICANT
CofO in Progress 9/10/2021 KENNETH NAGLE
Permit Finaled 9/10/2021 KENNETH NAGLE
CofO Issued 9/10/2021 KENNETH NAGLE
Permit Finaled 9/10/2021 KENNETH NAGLE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/15/2020 KIRK LINKLATER
Hold Cleared 12/3/2020 JASON SHEETS
Construction near power lines Cleared 12/9/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Azizisefat,, Solayman; Lic. No.: C57840 19510 VENTURA BLVD STE 110      TARZANA, CA 91356

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/11/2021 Partial Approval KEVIN SARGSYAN
Grading Pre-Inspection 2/11/2021 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 2/23/2021 Approved KEVIN SARGSYAN
Pool Piping 2/23/2021 Approved KEVIN SARGSYAN
Pre-Gunite 2/23/2021 Conditional Approval KEVIN SARGSYAN
Gas Piping or Gas Test 2/26/2021 Approved KEVIN SARGSYAN
Rough-Electrical 2/26/2021 Approved KEVIN SARGSYAN
Enclosure/Fence 4/6/2021 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/6/2021 SGSOV Not Ready KEVIN SARGSYAN
Enclosure/Fence 4/14/2021 Approved KEVIN SARGSYAN
Final 4/26/2021 Not Ready for Inspection KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/26/2021 SGSOV Not Ready KEVIN SARGSYAN
Pool Equipment Noise Test 4/27/2021 Approved ROBERT CHAVEZ
Final 4/29/2021 Conditional Approval KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/29/2021 SGSOV Approved KEVIN SARGSYAN