2762 S ARMACOST AVE 90064
Certificate Information: 2762 S ARMACOST AVE 90064
- Application / Permit
- 20047-10000-01041
- Plan Check / Job No.
- B20LA11984
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 28' X 14' POOL DEPTH WITH A MAX DEPTH OF 6', NEW 7' X 7' SPA WITH A MAX DEPTH OF 3'-6" PER STANDARD PLAN #268
- Permit Issued
- Issued on 1/25/2021
- Issuing Office
- Current Status
- CofO Issued on 7/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2020 | FERNANDO FLORES |
| Corrections Issued | 7/10/2020 | FERNANDO FLORES |
| Applicant returned to address corrections | 11/18/2020 | MANUEL GARCIA |
| Plan Check Approved | 1/19/2021 | GEORGE ALVAREZ |
| Issued | 1/25/2021 | APPLICANT |
| Building Plans Picked Up | 1/27/2021 | APPLICANT |
| CofO in Progress | 5/29/2026 | KIRK SANDERS |
| Permit Finaled | 7/14/2026 | RICHARD STEINBACH |
| CofO Issued | 7/14/2026 | RICHARD STEINBACH |
| Permit Finaled | 7/14/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/13/2020 | RIDWAN HARDY |
| Sewer availability | Cleared | 12/23/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | Horusicky Construction Inc; Lic. No.: 309844-C53 | P O BOX 3789 PALOS VERDES, CA 90274 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 2/1/2021 | Approved | OGANES TARAKHCHYAN |
| Enclosure/Fence | 6/2/2021 | Corrections Issued | KENNETH NAGLE |
| Enclosure/Fence | 6/28/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 5/12/2026 | Corrections Issued | KIRK SANDERS |
| Final | 5/12/2026 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 5/12/2026 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/12/2026 | SGSOV Approved | KIRK SANDERS |
| ELECTRICAL-Final | 5/21/2026 | Approved | KIRK SANDERS |
| Final | 5/21/2026 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 5/21/2026 | Approved | KIRK SANDERS |
| Pool Equipment Noise Test | 5/26/2026 | Approved | BRIAN CHRISTIAN |
| Final | 5/28/2026 | OK to Issue CofO | KIRK SANDERS |