4734 N HEAVEN AVE 91364
Certificate Information: 4734 N HEAVEN AVE 91364
- Application / Permit
- 20047-10000-01030
- Plan Check / Job No.
- B20LA11879
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- - EXISTING POOL - add new baja shelf within the existing shell of the pool and raise pool floor depth. - new baja shelf to be 10' feet by 12' feet. - existing pool floor depth is 8 feet and we are proposing to raise the pool floor to 4.5 feet will gunite.
- Permit Issued
- Issued on 7/28/2020
- Issuing Office
- Current Status
- Permit Finaled on 9/25/2020
Permit Application Status History
| Submitted | 7/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2020 | MONICA RAMIREZ |
| Corrections Issued | 7/13/2020 | MONICA RAMIREZ |
| Plan Check Approved | 7/23/2020 | MONICA RAMIREZ |
| Issued | 7/28/2020 | APPLICANT |
| Permit Finaled | 9/23/2020 | PAUL CHOPP |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | S C P Corporation; Lic. No.: 618217-C53 | PO BOX 8351 NORTHRIDGE, CA 91327 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 8/4/2020 | Corrections Issued | DAVID SANDOVAL |
| Grounding or Bonding | 8/7/2020 | Not Ready for Inspection | DONALD SUNSERI |
| Pre-Gunite | 8/7/2020 | Corrections Issued | DONALD SUNSERI |
| Grounding or Bonding | 8/10/2020 | Corrections Issued | DONALD SUNSERI |
| Pre-Gunite | 8/10/2020 | Not Ready for Inspection | DONALD SUNSERI |
| Grounding or Bonding | 8/11/2020 | Approved | DONALD SUNSERI |
| Pre-Gunite | 8/11/2020 | Approved | DONALD SUNSERI |
| Deputy Shotcrete | 8/13/2020 | No Access for Inspection | PAUL CHOPP |
| Enclosure/Fence | 9/4/2020 | Approved | RONALD COWAN |
| Final | 9/17/2020 | Corrections Issued | PAUL CHOPP |
| SGSOV-Seismic Gas S/O Valve | 9/17/2020 | SGSOV Approved | PAUL CHOPP |
| Equipment Noise Level | 9/22/2020 | Approved | ALFREDO FLORES |
| Final | 9/23/2020 | Permit Finaled | PAUL CHOPP |