6426 W VALMONT ST 91042

Certificate Information: 6426 W VALMONT ST 91042

Application / Permit
20047-10000-01027
Plan Check / Job No.
B20LA11858
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED POOL AND SPA PER STANDARD PLAN #268. 1 OF 2
Permit Issued
Issued on 2/4/2021
Issuing Office
Current Status
CofO Issued on 12/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2020 APPLICANT
Assigned to Plan Check Engineer 7/30/2020 MICHAEL LOPEZ
Corrections Issued 8/6/2020 MICHAEL LOPEZ
Quality Review Completed 9/14/2020 PRANITA SHAH
Building Plans Picked Up 9/21/2020 APPLICANT
Plan Check Approved 12/31/2020 MICHAEL LOPEZ
Issued 2/4/2021 APPLICANT
CofO in Progress 9/17/2021 MATTHEW NELSON
Permit Finaled 12/16/2021 RONALD MYRICK
CofO Issued 12/16/2021 RONALD MYRICK
Permit Finaled 12/16/2021 RONALD MYRICK

Permit Application Clearance Information

Sewer availability Cleared 10/21/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/23/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 12/30/2020 MICHAEL LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 2/22/2021 Not Ready for Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 3/8/2021 Corrections Issued MATTHEW NELSON
Pool Piping 4/20/2021 Approved MATTHEW NELSON
Pre-Gunite 4/20/2021 Approved MATTHEW NELSON
Rough-Electrical 4/20/2021 Approved MATTHEW NELSON
Rough-Plumbing 4/20/2021 Approved MATTHEW NELSON
Grounding or Bonding 5/5/2021 Corrections Issued GREGG CUMMINGS
Grounding or Bonding 5/10/2021 Corrections Issued MATTHEW NELSON
Grounding or Bonding 5/14/2021 No Access for Inspection MATTHEW NELSON
Grounding or Bonding 5/20/2021 Approved MATTHEW NELSON
Enclosure/Fence 8/17/2021 Corrections Issued MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 8/17/2021 Approved MATTHEW NELSON
Final 8/17/2021 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 8/17/2021 SGSOV Not Ready MATTHEW NELSON
Enclosure/Fence 8/26/2021 Approved MATTHEW NELSON
Final 8/26/2021 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 8/26/2021 SGSOV Not Ready MATTHEW NELSON
Final 9/14/2021 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 9/14/2021 SGSOV Not Ready MATTHEW NELSON
ELECTRICAL-Final 9/16/2021 Approved MATTHEW NELSON
Final 9/16/2021 OK to Issue CofO MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 9/16/2021 SGSOV Approved MATTHEW NELSON