221 S LUCERNE BLVD 90004

Certificate Information: 221 S LUCERNE BLVD 90004

Application / Permit
20047-10000-00904
Plan Check / Job No.
B20LA10815
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA 19' X 26' WITH POOL COVER USING STANDARD PLAN 268 AND DETAIL #672
Permit Issued
Issued on 7/17/2020
Issuing Office
Current Status
CofO Issued on 12/10/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2020 APPLICANT
Assigned to Plan Check Engineer 6/22/2020 SINA KHOSRAVI
Corrections Issued 6/22/2020 SINA KHOSRAVI
Plan Check Approved 7/17/2020 AMIR DANAI
Issued 7/17/2020 APPLICANT
Building Plans Picked Up 8/3/2020 APPLICANT
CofO in Progress 12/8/2020 ELMER BLAND
Permit Finaled 12/10/2020 DEROLD HAUFF
CofO Issued 12/10/2020 DEROLD HAUFF
Permit Finaled 12/10/2020 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 6/26/2020 LYDIA CHAPMAN
CPC Cleared 6/26/2020 LYDIA CHAPMAN
CPC Cleared 6/26/2020 LYDIA CHAPMAN
HPOZ Cleared 6/26/2020 LYDIA CHAPMAN
Construction near power lines Cleared 6/29/2020 OSCAR CASTRO

Contact Information

Contractor Marten Darin Construction Company; Lic. No.: 525472-C-8 P O BOX 659      PACIFIC PALISADES, CA 90272
Contractor Marten Darin Construction Company; Lic. No.: 525472-C53 P O BOX 659      PACIFIC PALISADES, CA 90272
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 8/18/2020 Approved ARTHUR SARGSYAN
Rough-Electrical 8/18/2020 Approved ARTHUR SARGSYAN
Rough-Plumbing 8/18/2020 Approved ARTHUR SARGSYAN
Deck 10/13/2020 Approved ARTHUR SARGSYAN
Enclosure/Fence 10/13/2020 Approved ARTHUR SARGSYAN
Final 11/9/2020 No Access for Inspection DONALD CRICHLOW
SGSOV-Seismic Gas S/O Valve 11/9/2020 SGSOV Not Ready DONALD CRICHLOW
Final 11/17/2020 Not Ready for Inspection DONALD CRICHLOW
SGSOV-Seismic Gas S/O Valve 11/17/2020 SGSOV Not Ready DONALD CRICHLOW
Final 11/24/2020 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 11/24/2020 SGSOV Approved SCOTT FINNILA
Pool Equipment Noise Test 12/1/2020 Approved ROBERT CHAVEZ
ELECTRICAL-Final 12/8/2020 Approved ELMER BLAND
Final 12/8/2020 OK to Issue CofO ELMER BLAND
PLUMBING-Final 12/8/2020 Approved ELMER BLAND