221 S LUCERNE BLVD 90004
Certificate Information: 221 S LUCERNE BLVD 90004
- Application / Permit
- 20047-10000-00904
- Plan Check / Job No.
- B20LA10815
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL AND SPA 19' X 26' WITH POOL COVER USING STANDARD PLAN 268 AND DETAIL #672
- Permit Issued
- Issued on 7/17/2020
- Issuing Office
- Current Status
- CofO Issued on 12/10/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2020 | SINA KHOSRAVI |
| Corrections Issued | 6/22/2020 | SINA KHOSRAVI |
| Plan Check Approved | 7/17/2020 | AMIR DANAI |
| Issued | 7/17/2020 | APPLICANT |
| Building Plans Picked Up | 8/3/2020 | APPLICANT |
| CofO in Progress | 12/8/2020 | ELMER BLAND |
| Permit Finaled | 12/10/2020 | DEROLD HAUFF |
| CofO Issued | 12/10/2020 | DEROLD HAUFF |
| Permit Finaled | 12/10/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 6/26/2020 | LYDIA CHAPMAN |
| CPC | Cleared | 6/26/2020 | LYDIA CHAPMAN |
| CPC | Cleared | 6/26/2020 | LYDIA CHAPMAN |
| HPOZ | Cleared | 6/26/2020 | LYDIA CHAPMAN |
| Construction near power lines | Cleared | 6/29/2020 | OSCAR CASTRO |
Contact Information
| Contractor | Marten Darin Construction Company; Lic. No.: 525472-C-8 | P O BOX 659 PACIFIC PALISADES, CA 90272 |
| Contractor | Marten Darin Construction Company; Lic. No.: 525472-C53 | P O BOX 659 PACIFIC PALISADES, CA 90272 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 8/18/2020 | Approved | ARTHUR SARGSYAN |
| Rough-Electrical | 8/18/2020 | Approved | ARTHUR SARGSYAN |
| Rough-Plumbing | 8/18/2020 | Approved | ARTHUR SARGSYAN |
| Deck | 10/13/2020 | Approved | ARTHUR SARGSYAN |
| Enclosure/Fence | 10/13/2020 | Approved | ARTHUR SARGSYAN |
| Final | 11/9/2020 | No Access for Inspection | DONALD CRICHLOW |
| SGSOV-Seismic Gas S/O Valve | 11/9/2020 | SGSOV Not Ready | DONALD CRICHLOW |
| Final | 11/17/2020 | Not Ready for Inspection | DONALD CRICHLOW |
| SGSOV-Seismic Gas S/O Valve | 11/17/2020 | SGSOV Not Ready | DONALD CRICHLOW |
| Final | 11/24/2020 | Corrections Issued | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 11/24/2020 | SGSOV Approved | SCOTT FINNILA |
| Pool Equipment Noise Test | 12/1/2020 | Approved | ROBERT CHAVEZ |
| ELECTRICAL-Final | 12/8/2020 | Approved | ELMER BLAND |
| Final | 12/8/2020 | OK to Issue CofO | ELMER BLAND |
| PLUMBING-Final | 12/8/2020 | Approved | ELMER BLAND |