736 E AMOROSO PL 90291
Certificate Information: 736 E AMOROSO PL 90291
- Application / Permit
- 20047-10000-00887
- Plan Check / Job No.
- B20LA10639
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Eplan. New swimming pool and spa per City of Los Angeles standard plan # 268.
- Permit Issued
- Issued on 9/28/2020
- Issuing Office
- Current Status
- CofO Issued on 3/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2020 | HELEN NGUYEN |
| Corrections Issued | 6/22/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 7/14/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/24/2020 | MONICA RAMIREZ |
| Plan Check Approved | 9/24/2020 | HELEN NGUYEN |
| Issued | 9/28/2020 | APPLICANT |
| CofO in Progress | 2/25/2021 | PIERRE VEGA |
| CofO Issued | 3/3/2021 | VINCENT COTTON |
| Permit Finaled | 3/3/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/17/2020 | ANACANY HURTADO |
| Miscellaneous | Cleared | 7/17/2020 | ANACANY HURTADO |
| Miscellaneous | Cleared | 7/17/2020 | ANACANY HURTADO |
| Miscellaneous | Cleared | 7/17/2020 | ANACANY HURTADO |
| ZA Case | Cleared | 7/17/2020 | ANACANY HURTADO |
| ZI | Cleared | 7/21/2020 | LAMBERT GIESSINGER |
| Coastal Zone | Cleared | 9/17/2020 | ANACANY HURTADO |
Contact Information
| Contractor | Pepe'S Pools Inc; Lic. No.: 1028041-C53 | 4817 YORK BLVD LOS ANGELES, CA 90042 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/4/2020 | Partial Approval | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 11/12/2020 | Approved | DAVID HEINE |
| Pre-Gunite | 11/12/2020 | Approved | DAVID HEINE |
| Grounding or Bonding | 12/22/2020 | Approved | DAVID HEINE |
| Enclosure/Fence | 1/12/2021 | Corrections Issued | DAVID HEINE |
| Enclosure/Fence | 1/13/2021 | Approved | DAVID HEINE |
| Final | 1/21/2021 | Corrections Issued | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 1/21/2021 | SGSOV Approved | DAVID HEINE |
| Final | 2/9/2021 | Partial Approval | JOHNNY MIRANDA |
| Special/Order Compliance | 3/1/2021 | Approved | JOHNNY MIRANDA |