17524 W COHASSET ST 91406

Certificate Information: 17524 W COHASSET ST 91406

Application / Permit
20047-10000-00850
Plan Check / Job No.
B20LA10306
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA PER STD PLAN #268.
Permit Issued
Issued on 9/11/2020
Issuing Office
Current Status
CofO Issued on 9/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2020 APPLICANT
Assigned to Plan Check Engineer 6/15/2020 CRISTINA SALAZAR
Corrections Issued 6/29/2020 CRISTINA SALAZAR
Applicant returned to address corrections 7/20/2020 RICARDO RAMIREZ
Applicant returned to address corrections 8/31/2020 RICARDO RAMIREZ
Issued 9/11/2020 APPLICANT
Building Plans Picked Up 9/15/2020 APPLICANT
CofO in Progress 9/8/2022 MICHAEL SMITH
CofO in Progress 9/8/2022 MICHAEL SMITH
CofO Issued 9/8/2022 MICHAEL SMITH
Permit Finaled 9/8/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/24/2020 ADRIAN CASTRO
Sewer availability Cleared 6/24/2020 ADRIAN CASTRO
Construction near power lines Cleared 9/9/2020 WALTER RAMIREZ

Contact Information

Contractor Picasso Pools & Outdoor Living Llc; Lic. No.: 1056888-C53 17418 KINGSBURY ST      GRANADA HILLS, CA 91344
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 9/23/2020 Approved JOSEPH SAGEN
Pool Piping 9/23/2020 Approved JOSEPH SAGEN
Pre-Gunite 9/23/2020 Approved JOSEPH SAGEN
Rough-Electrical 9/23/2020 Partial Approval JOSEPH SAGEN
Deck 10/26/2020 Approved MICHAEL TEMPLE
Enclosure/Fence 11/5/2020 Approved ARTHUR SARGSYAN
Equipment Noise Level 12/10/2020 Approved ALFREDO FLORES
Final 12/21/2020 Partial Approval ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/21/2020 SGSOV Approved ARTHUR SARGSYAN
Final 9/8/2022 OK to Issue CofO MICHAEL SMITH
Special/Order Compliance 9/8/2022 Approved MICHAEL SMITH