1859 N MCCOLLUM ST 90026

Certificate Information: 1859 N MCCOLLUM ST 90026

Application / Permit
20047-10000-00789
Plan Check / Job No.
B20LA09861
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ALTER (E) POOL, NEW SPA + WATER FEATURE
Permit Issued
Issued on 6/22/2021
Issuing Office
Current Status
Issued on 6/22/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/4/2020 APPLICANT
Assigned to Plan Check Engineer 6/26/2020 CARLOS MONTES
Corrections Issued 6/29/2020 CARLOS MONTES
Quality Review Completed 7/24/2020 PRANITA SHAH
Applicant returned to address corrections 10/1/2020 CARLOS MONTES
Applicant returned to address corrections 10/21/2020 CARLOS MONTES
Applicant returned to address corrections 1/21/2021 CARLOS MONTES
Applicant returned to address corrections 3/4/2021 CARLOS MONTES
Applicant returned to address corrections 4/19/2021 CARLOS MONTES
Plan Check Approved 6/10/2021 CARLOS MONTES
Issued 6/22/2021 APPLICANT
Building Plans Picked Up 6/24/2021 APPLICANT

Permit Application Clearance Information

Low Impact Development Cleared 9/23/2020 MARTIN FRAGOSO
Grading Pre-Inspection Cleared 10/21/2020 CARLOS MONTES

Contact Information

Contractor Royal Moon Pools Inc; Lic. No.: 1041907-C53 2518 SAN MACHID WAY      ROSAMOND, CA 93560
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401
Engineer Gorgy,, Moheb Shohdy; Lic. No.: C53260 1545 VICTORY BLVD STE 102      GLENDALE, CA 91201
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Geologist Kruger,, Mark Otto; Lic. No.: EG2345 10120 NATIONAL BLVD      LOS ANGELES, CA 90034

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 11/2/2021 Corrections Issued THOMAS LOGRASSO
Pre-Gunite 11/4/2021 Corrections Issued THOMAS LOGRASSO
Pre-Gunite 11/8/2021 Corrections Issued THOMAS LOGRASSO
Pre-Gunite 1/31/2022 Corrections Issued THOMAS LOGRASSO
Pre-Gunite 2/15/2022 Not Ready for Inspection THOMAS LOGRASSO
Pre-Gunite 2/22/2022 Approved THOMAS LOGRASSO
Deputy Shotcrete 3/9/2022 Conditional Approval RUBEN SALAS
Deck 10/6/2023 Not Ready for Inspection THOMAS LOGRASSO
Grounding or Bonding 10/6/2023 Not Ready for Inspection THOMAS LOGRASSO
Special/Order Compliance 10/6/2023 Corrections Issued THOMAS LOGRASSO
Deck 10/13/2023 Partial Inspection STUART CHAPMAN
Grounding or Bonding 10/13/2023 Partial Inspection STUART CHAPMAN
Pre-Inspection 2/16/2024 Corrections Issued THOMAS LOGRASSO
Special/Order Compliance 2/22/2024 Not Ready for Inspection THOMAS LOGRASSO
Pre-Inspection 3/13/2024 Partial Inspection THOMAS LOGRASSO
Deck 5/21/2024 Approved HAMIK HARTOUNIAN
Pre-Inspection 5/21/2024 Partial Inspection HAMIK HARTOUNIAN
Enclosure/Fence 2/5/2026 Corrections Issued HAMIK HARTOUNIAN
Enclosure/Fence 2/9/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Enclosure/Fence 2/20/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Enclosure/Fence 2/24/2026 Approved HAMIK HARTOUNIAN
Final 3/4/2026 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/4/2026 SGSOV Approved HAMIK HARTOUNIAN