6601 N PETIT AVE 91406

Certificate Information: 6601 N PETIT AVE 91406

Application / Permit
20047-10000-00708
Plan Check / Job No.
B20LA09256
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ePlan Swimming pool. New Swimming Pool and Spa per standard plan 268
Permit Issued
Issued on 5/24/2021
Issuing Office
Current Status
CofO Issued on 3/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2020 APPLICANT
Assigned to Plan Check Engineer 5/26/2020 MONICA RAMIREZ
Corrections Issued 5/26/2020 MONICA RAMIREZ
Plan Check Approved 5/18/2021 MONICA RAMIREZ
Issued 5/24/2021 APPLICANT
CofO in Progress 2/6/2024 RAUL OLAGI
Permit Finaled 3/6/2024 RUBEN SALAS
CofO Issued 3/6/2024 RUBEN SALAS
Permit Finaled 3/6/2024 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 2/16/2021 WALTER RAMIREZ
Construction within easement Cleared 2/16/2021 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/6/2021 LEE GUILBEAUX
Watercourse Cleared 5/6/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/6/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Biedenbach,, Christopher James; Lic. No.: NA74003       ,

Inspector Information

KIRK SANDERS, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/25/2021 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 6/2/2021 Partial Inspection ARTHUR SARGSYAN
Pre-Gunite 6/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
Rough-Electrical 6/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
Rough-Plumbing 6/2/2021 Not Ready for Inspection ARTHUR SARGSYAN
Grounding or Bonding 6/8/2021 Approved ARTHUR SARGSYAN
Rough-Electrical 6/8/2021 Not Ready for Inspection ARTHUR SARGSYAN
Rough-Plumbing 6/8/2021 Not Ready for Inspection ARTHUR SARGSYAN
Gunite 6/14/2021 Approved ARTHUR SARGSYAN
Pre-Gunite 6/14/2021 Approved ARTHUR SARGSYAN
Rough-Electrical 6/14/2021 Approved ARTHUR SARGSYAN
Rough-Plumbing 6/14/2021 Approved ARTHUR SARGSYAN
Deputy Other (see comments) 6/24/2021 Approved JAVIER RAMOS JR
Gunite 6/29/2021 Not Ready for Inspection JACK KARGODORIAN
Gas Piping or Gas Test 7/19/2021 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Final 7/19/2021 Approved JACK KARGODORIAN
Grounding or Bonding 8/13/2021 Not Ready for Inspection JACK KARGODORIAN
Deck 8/17/2021 Approved JACK KARGODORIAN
Grounding or Bonding 8/17/2021 Approved JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 11/4/2022 Approved RAUL OLAGI
Final 11/4/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 11/4/2022 SGSOV Approved RAUL OLAGI
Equipment Noise Level 1/24/2024 Approved FELIPE PENICHE
Pool Equipment Noise Test 1/24/2024 Approved FELIPE PENICHE
Final 2/6/2024 OK to Issue CofO RAUL OLAGI