6601 N PETIT AVE 91406
Certificate Information: 6601 N PETIT AVE 91406
- Application / Permit
- 20047-10000-00708
- Plan Check / Job No.
- B20LA09256
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan Swimming pool. New Swimming Pool and Spa per standard plan 268
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Current Status
- CofO Issued on 3/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2020 | MONICA RAMIREZ |
| Corrections Issued | 5/26/2020 | MONICA RAMIREZ |
| Plan Check Approved | 5/18/2021 | MONICA RAMIREZ |
| Issued | 5/24/2021 | APPLICANT |
| CofO in Progress | 2/6/2024 | RAUL OLAGI |
| Permit Finaled | 3/6/2024 | RUBEN SALAS |
| CofO Issued | 3/6/2024 | RUBEN SALAS |
| Permit Finaled | 3/6/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/16/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 2/16/2021 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2021 | LEE GUILBEAUX |
| Watercourse | Cleared | 5/6/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/6/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: NA74003 | , |
Inspector Information
| KIRK SANDERS, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/25/2021 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 6/2/2021 | Partial Inspection | ARTHUR SARGSYAN |
| Pre-Gunite | 6/2/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Rough-Electrical | 6/2/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Rough-Plumbing | 6/2/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Grounding or Bonding | 6/8/2021 | Approved | ARTHUR SARGSYAN |
| Rough-Electrical | 6/8/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Rough-Plumbing | 6/8/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Gunite | 6/14/2021 | Approved | ARTHUR SARGSYAN |
| Pre-Gunite | 6/14/2021 | Approved | ARTHUR SARGSYAN |
| Rough-Electrical | 6/14/2021 | Approved | ARTHUR SARGSYAN |
| Rough-Plumbing | 6/14/2021 | Approved | ARTHUR SARGSYAN |
| Deputy Other (see comments) | 6/24/2021 | Approved | JAVIER RAMOS JR |
| Gunite | 6/29/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Gas Piping or Gas Test | 7/19/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Final | 7/19/2021 | Approved | JACK KARGODORIAN |
| Grounding or Bonding | 8/13/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Deck | 8/17/2021 | Approved | JACK KARGODORIAN |
| Grounding or Bonding | 8/17/2021 | Approved | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 11/4/2022 | Approved | RAUL OLAGI |
| Final | 11/4/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 11/4/2022 | SGSOV Approved | RAUL OLAGI |
| Equipment Noise Level | 1/24/2024 | Approved | FELIPE PENICHE |
| Pool Equipment Noise Test | 1/24/2024 | Approved | FELIPE PENICHE |
| Final | 2/6/2024 | OK to Issue CofO | RAUL OLAGI |