24320 S STERLING RANCH ROAD 91304
Certificate Information: 24320 S STERLING RANCH ROAD 91304
- Application / Permit
- 20047-10000-00684
- Plan Check / Job No.
- B20LA09107
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL AND SPA PER LA CITY STANDARD PLAN # 270.
- Permit Issued
- Issued on 7/28/2020
- Issuing Office
- Current Status
- CofO Issued on 2/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2020 | CRISTINA SALAZAR |
| Corrections Issued | 5/22/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 6/30/2020 | JESSE JIMENEZ |
| Plan Check Approved | 7/6/2020 | JESSE JIMENEZ |
| Building Plans Picked Up | 7/6/2020 | APPLICANT |
| Issued | 7/28/2020 | APPLICANT |
| CofO in Progress | 2/3/2021 | DAVID STEPANYAN |
| CofO Issued | 2/23/2021 | JOHN JANSON |
| Permit Finaled | 2/23/2021 | JOHN JANSON |
Permit Application Clearance Information
| ZA Case | Cleared | 6/18/2020 | MIGUEL GAMBOA |
| Sewer availability | Cleared | 6/19/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | My Town Building And Remodeling; Lic. No.: 1036847-B | 2807 W AVE M12 PALMDALE, CA 93551 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/5/2020 | Corrections Issued | DAVID STEPANYAN |
| Rough-Electrical | 8/5/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Rough-Plumbing | 8/5/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 8/10/2020 | Approved | DAVID STEPANYAN |
| Rough-Electrical | 8/10/2020 | Approved | DAVID STEPANYAN |
| Rough-Plumbing | 8/10/2020 | Approved | DAVID STEPANYAN |
| Deputy Shotcrete | 8/12/2020 | Conditional Approval | DAVID STEPANYAN |
| Pool Piping | 8/17/2020 | Corrections Issued | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 1/19/2021 | SGSOV Not Ready | TROY SANDERS |
| Pool Equipment Noise Test | 1/25/2021 | Approved | FELIPE PENICHE |
| Deck | 2/2/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 2/2/2021 | Approved | DAVID STEPANYAN |
| Enclosure/Fence | 2/2/2021 | Approved | DAVID STEPANYAN |
| Final | 2/2/2021 | OK to Issue CofO | DAVID STEPANYAN |
| Pool Piping | 2/2/2021 | Approved | DAVID STEPANYAN |
| Pre-Gunite | 2/2/2021 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 2/2/2021 | SGSOV Approved | DAVID STEPANYAN |