3477 N BEVERLY GLEN BLVD 91423

Certificate Information: 3477 N BEVERLY GLEN BLVD 91423

Application / Permit
20047-10000-00464
Plan Check / Job No.
B20LA06115
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 140 SF SWIMMING POOL, WITH ATTACHED 42 SF SPA STD PLAN #268
Permit Issued
Issued on 5/8/2020
Issuing Office
Current Status
CofO Issued on 10/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2020 APPLICANT
Assigned to Plan Check Engineer 4/7/2020 LUKE GONZALES
Corrections Issued 4/7/2020 LUKE GONZALES
Plan Check Approved 5/7/2020 LUKE GONZALES
Issued 5/8/2020 APPLICANT
Building Plans Picked Up 5/12/2020 APPLICANT
Permit Finaled 10/9/2024 DANIEL ORRANTE
CofO Issued 10/9/2024 DANIEL ORRANTE
Permit Finaled 10/9/2024 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 4/20/2020 DANG NGUYEN
ZI Cleared 4/20/2020 DANG NGUYEN
Grading Pre-Inspection Cleared 4/28/2020 PATRICK MISCHLICH

Contact Information

Contractor S H Pools Inc; Lic. No.: 779265-B 25511 RHODA DRIVE      MISSION VIEJO, CA 92691

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/29/2020 Approved DANIEL ORRANTE
Gas Piping or Gas Test 5/29/2020 Approved DANIEL ORRANTE
Grounding or Bonding 5/29/2020 Approved DANIEL ORRANTE
Pool Piping 5/29/2020 Approved DANIEL ORRANTE
Pre-Gunite 5/29/2020 Corrections Issued DANIEL ORRANTE
Rough-Electrical 5/29/2020 Approved DANIEL ORRANTE
Rough-Plumbing 5/29/2020 Approved DANIEL ORRANTE
Grounding or Bonding 6/3/2020 Partial Approval THOMAS FINNILA
Pre-Gunite 6/3/2020 Conditional Approval THOMAS FINNILA
Deck 6/19/2020 Approved CHARLES POWELL
Grounding or Bonding 6/19/2020 Approved CHARLES POWELL
Enclosure/Fence 8/6/2020 Approved CHARLES POWELL
Gunite 8/6/2020 Approved CHARLES POWELL
Final 8/13/2020 Corrections Issued CHARLES POWELL
Pre-Gunite 8/13/2020 Approved CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 8/13/2020 SGSOV Not Ready CHARLES POWELL
Final 8/18/2020 Partial Approval CHARLES POWELL