3477 N BEVERLY GLEN BLVD 91423
Certificate Information: 3477 N BEVERLY GLEN BLVD 91423
- Application / Permit
- 20047-10000-00464
- Plan Check / Job No.
- B20LA06115
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 140 SF SWIMMING POOL, WITH ATTACHED 42 SF SPA STD PLAN #268
- Permit Issued
- Issued on 5/8/2020
- Issuing Office
- Current Status
- CofO Issued on 10/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2020 | LUKE GONZALES |
| Corrections Issued | 4/7/2020 | LUKE GONZALES |
| Plan Check Approved | 5/7/2020 | LUKE GONZALES |
| Issued | 5/8/2020 | APPLICANT |
| Building Plans Picked Up | 5/12/2020 | APPLICANT |
| Permit Finaled | 10/9/2024 | DANIEL ORRANTE |
| CofO Issued | 10/9/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/9/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/20/2020 | DANG NGUYEN |
| ZI | Cleared | 4/20/2020 | DANG NGUYEN |
| Grading Pre-Inspection | Cleared | 4/28/2020 | PATRICK MISCHLICH |
Contact Information
| Contractor | S H Pools Inc; Lic. No.: 779265-B | 25511 RHODA DRIVE MISSION VIEJO, CA 92691 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/29/2020 | Approved | DANIEL ORRANTE |
| Gas Piping or Gas Test | 5/29/2020 | Approved | DANIEL ORRANTE |
| Grounding or Bonding | 5/29/2020 | Approved | DANIEL ORRANTE |
| Pool Piping | 5/29/2020 | Approved | DANIEL ORRANTE |
| Pre-Gunite | 5/29/2020 | Corrections Issued | DANIEL ORRANTE |
| Rough-Electrical | 5/29/2020 | Approved | DANIEL ORRANTE |
| Rough-Plumbing | 5/29/2020 | Approved | DANIEL ORRANTE |
| Grounding or Bonding | 6/3/2020 | Partial Approval | THOMAS FINNILA |
| Pre-Gunite | 6/3/2020 | Conditional Approval | THOMAS FINNILA |
| Deck | 6/19/2020 | Approved | CHARLES POWELL |
| Grounding or Bonding | 6/19/2020 | Approved | CHARLES POWELL |
| Enclosure/Fence | 8/6/2020 | Approved | CHARLES POWELL |
| Gunite | 8/6/2020 | Approved | CHARLES POWELL |
| Final | 8/13/2020 | Corrections Issued | CHARLES POWELL |
| Pre-Gunite | 8/13/2020 | Approved | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 8/13/2020 | SGSOV Not Ready | CHARLES POWELL |
| Final | 8/18/2020 | Partial Approval | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 8/18/2020 | SGSOV Approved | CHARLES POWELL |