1027 W WILSHIRE BLVD 90017

Certificate Information: 1027 W WILSHIRE BLVD 90017

Application / Permit
20047-10000-00071
Plan Check / Job No.
B20LA00847
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
Commercial
Primary Use
(4) Pool/Spa - Public
Work Description
NEW MOAT POOL.
Permit Issued
Issued on 10/21/2020
Issuing Office
Current Status
Permit Finaled on 7/28/2021
Certificate of Occupancy
TCO Issued More Information

Permit Application Status History

Submitted 1/16/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 ERWIN PASCUA
Corrections Issued 2/27/2020 ERWIN PASCUA
Disabled Access Plans Picked Up 2/28/2020 APPLICANT
Quality Review Completed 3/2/2020 CHARLES CHANG
Building Plans Picked Up 3/13/2020 APPLICANT
Applicant returned to address corrections 7/1/2020 ERWIN PASCUA
Applicant returned to address corrections 10/20/2020 ERWIN PASCUA
Plan Check Approved 10/21/2020 ERWIN PASCUA
Issued 10/21/2020 APPLICANT
Permit Finaled 7/28/2021 ERNESTO CORRAL

Permit Application Clearance Information

CPC Cleared 7/21/2020 SARAHI ORTEGA
Tract Map conditions Cleared 7/21/2020 SARAHI ORTEGA
Tract Map conditions Cleared 7/21/2020 SARAHI ORTEGA
ZA Case Cleared 7/21/2020 SARAHI ORTEGA
ZA Case Cleared 7/21/2020 SARAHI ORTEGA
ZA Case Cleared 7/21/2020 SARAHI ORTEGA
ZA Case Cleared 7/21/2020 SARAHI ORTEGA
Public Swimming Pool approval Cleared 9/15/2020 LACDHS APPROVED
DAS Clearance Cleared 9/21/2020 ERWIN PASCUA
Specific Plan Cleared 9/30/2020 ERWIN PASCUA
ZI Cleared 9/30/2020 ERWIN PASCUA
Eng Process Fee Ord 176,300 Cleared 10/9/2020 CECILIO NAVARRO
Sewer availability Cleared 10/9/2020 CECILIO NAVARRO

Contact Information

Contractor Sapphire Pool & Spa Construction; Lic. No.: 907319-C53 109 E AVENIDA DE LOS LOBOS   MARINOS    SAN CLEMENTE, CA 92672
Engineer Lenehan,, Kyle Aaron; Lic. No.: C82227 11853 WHITE RAIN WAY      RANCHO CORDOVA, CA 95742

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/5/2020 Not Ready for Inspection NICK DANERI
Pre-Gunite 11/5/2020 Not Ready for Inspection NICK DANERI
Grounding or Bonding 11/6/2020 Not Ready for Inspection NICK DANERI
Pre-Gunite 11/12/2020 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 4/21/2021 Approved NICK DANERI
Final 4/21/2021 Partial Inspection NICK DANERI
Pre-Gunite 4/21/2021 Approved NICK DANERI
SGSOV-Seismic Gas S/O Valve 4/21/2021 SGSOV Not Ready NICK DANERI
Final 7/12/2021 Conditional Approval DANIEL COLLINS
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Approved DANIEL COLLINS
Final 7/20/2021 Conditional Approval ERNESTO CORRAL
Final 7/28/2021 Conditional Approval ERNESTO CORRAL