9049 W CRESTA DR 90035

Certificate Information: 9049 W CRESTA DR 90035

Application / Permit
20030-30000-06890
Plan Check / Job No.
B20WL05257
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
Grading for (N) SFD & shoring. Remove & recompact. See comments.
Permit Issued
Issued on 12/7/2020
Issuing Office
Current Status
Permit Finaled on 8/8/2025

Permit Application Status History

Plan Check Approved 12/2/2020 VLADIMIR ARUTYUNYAN
Issued 12/7/2020 APPLICANT
Building Plans Picked Up 12/8/2020 APPLICANT
Permit Finaled 8/8/2025 MATTHEW JENKINS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 12/10/2020 Corrections Issued JONATHAN HOM
Bottom/Toe 3/8/2021 Partial Inspection MATTHEW JENKINS
Excavation 3/8/2021 Corrections Issued MATTHEW JENKINS
Initial Grading 3/8/2021 Partial Inspection MATTHEW JENKINS
Sub-Drain 3/24/2021 Not Ready for Inspection MATTHEW JENKINS
Bottom/Toe 3/26/2021 Not Ready for Inspection KIRK LINKLATER
Rough 3/26/2021 Not Ready for Inspection KIRK LINKLATER
Sub-Drain 3/26/2021 Conditional Approval KIRK LINKLATER
Fill/Backfill 6/29/2021 No Access for Inspection AL GAMBLE
Sub-Drain 6/29/2021 No Access for Inspection AL GAMBLE
Fill/Backfill 7/1/2021 Partial Inspection JONATHAN HOM
Sub-Drain 7/1/2021 Partial Approval JONATHAN HOM
Fill/Backfill 7/8/2021 Not Ready for Inspection AL GAMBLE
Sub-Drain 7/8/2021 Not Ready for Inspection AL GAMBLE
Approved Compaction Report 3/8/2023 Corrections Issued MATTHEW JENKINS
Approved Compaction Report 3/24/2023 Corrections Issued MATTHEW JENKINS
Approved Compaction Report 5/17/2023 Approved MATTHEW JENKINS
Bottom/Toe 6/7/2023 Partial Inspection MATTHEW JENKINS
Final 6/7/2023 Corrections Issued MATTHEW JENKINS
Rough 6/7/2023 Partial Inspection MATTHEW JENKINS
Bottom/Toe 6/15/2023 Partial Inspection RUSSELL BONVOULOIR
Final 6/15/2023 Partial Inspection RUSSELL BONVOULOIR
Rough 6/15/2023 Partial Inspection RUSSELL BONVOULOIR
Approved Compaction Report 2/23/2024 Approved VASIL MIHALEV
Bottom/Toe 3/11/2024 Partial Inspection MATTHEW JENKINS
Final 3/11/2024 Corrections Issued MATTHEW JENKINS
Rough 3/11/2024 Partial Inspection MATTHEW JENKINS
Bottom/Toe 9/23/2024 Partial Inspection MATTHEW JENKINS
Final 9/23/2024 Not Ready for Inspection MATTHEW JENKINS
Rough 9/23/2024 Partial Inspection MATTHEW JENKINS
Bottom/Toe 8/8/2025 Approved MATTHEW JENKINS
Final 8/8/2025 Permit Finaled MATTHEW JENKINS