1750 N WESTRIDGE ROAD 90049
Certificate Information: 1750 N WESTRIDGE ROAD 90049
- Application / Permit
- 20030-30000-06774
- Plan Check / Job No.
- B20WL05157
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING FOR BASEMENT ADDITIONS
- Permit Issued
- Issued on 4/29/2022
- Issuing Office
- Current Status
- Permit Finaled on 10/24/2025
Permit Application Status History
| Submitted | 12/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2020 | REZA HAGHIGHAT |
| Corrections Issued | 12/28/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 1/7/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/24/2021 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 12/2/2021 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 1/6/2022 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 1/27/2022 | REZA HAGHIGHAT |
| Building Plans Picked Up | 2/14/2022 | APPLICANT |
| Plan Check Approved | 4/29/2022 | REZA HAGHIGHAT |
| Issued | 4/29/2022 | APPLICANT |
| Permit Finaled | 10/23/2025 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2021 | DINAH GARIN |
| Work Adjacent to Public Way | Cleared | 6/29/2021 | SAUL GARCIA |
| Miscellaneous | Cleared | 10/14/2021 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 12/2/2021 | REZA HAGHIGHAT |
| Haul Route | Cleared | 12/2/2021 | REZA HAGHIGHAT |
| Excavation more than 5-ft deep | Cleared | 4/29/2022 | CALOSHA APPROVED |
Contact Information
| Architect | Burdge,, Douglas W; Lic. No.: C16899 | 24911 PACIFIC COAST HWY MALIBU, CA 90265 |
| Contractor | Owner-Builder | , |
| Engineer | Liston,, Leonard Irvin; Lic. No.: C31902 | 889 PIERCE CT STE 101 THOUSAND OAKS, CA 91360 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| RAMAZANALI ALMASI, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 5/11/2022 | Approved | TIMOTHY POWELL |
| Sub-Drain | 11/30/2023 | Corrections Issued | JOHNNY MIRANDA |
| Sub-Drain | 12/7/2023 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 12/6/2024 | Not Ready for Inspection | VASIL MIHALEV |
| Final | 12/6/2024 | Not Ready for Inspection | VASIL MIHALEV |
| Rough | 12/6/2024 | Not Ready for Inspection | VASIL MIHALEV |
| Approved Compaction Report | 4/18/2025 | Corrections Issued | MATTHEW JENKINS |
| Approved Compaction Report | 8/27/2025 | Approved | LANNY MERRICK |
| Approved Compaction Report | 9/4/2025 | Corrections Issued | MATTHEW JENKINS |
| Approved Compaction Report | 9/22/2025 | Approved | LANNY MERRICK |
| Bottom/Toe | 10/8/2025 | Approved | JOHNNY MIRANDA |
| Final | 10/8/2025 | Partial Inspection | JOHNNY MIRANDA |
| Rough | 10/8/2025 | Approved | JOHNNY MIRANDA |
| Final | 10/23/2025 | Permit Finaled | JOHNNY MIRANDA |