10590 W CHEVIOT DR 90064

Certificate Information: 10590 W CHEVIOT DR 90064

Application / Permit
20030-30000-06737
Plan Check / Job No.
B20WL00285
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
REMOVAL AND RECOMPACTION FOR NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
Permit Issued
Issued on 3/31/2021
Issuing Office
Current Status
Permit Finaled on 10/26/2022

Permit Application Status History

Submitted 1/21/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 SERGIO SILVA
Corrections Issued 3/12/2020 SERGIO SILVA
Quality Review Completed 3/18/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 4/1/2020 APPLICANT
Applicant returned to address corrections 11/23/2020 SERGIO SILVA
Applicant returned to address corrections 1/15/2021 SERGIO SILVA
Applicant returned to address corrections 1/28/2021 SERGIO SILVA
Plan Check Approved 2/8/2021 SERGIO SILVA
Building Plans Picked Up 3/1/2021 APPLICANT
Issued 3/31/2021 APPLICANT
Permit Finaled 10/25/2022 AL GAMBLE

Permit Application Clearance Information

GPI Written Notices Cleared 11/23/2020 SERGIO SILVA
Grading Pre-Inspection Cleared 11/23/2020 SERGIO SILVA
Miscellaneous Cleared 11/23/2020 SERGIO SILVA
Miscellaneous Cleared 11/23/2020 SERGIO SILVA
Specific Plan Cleared 1/4/2021 FREDDY GARCIA
Miscellaneous Cleared 1/15/2021 SERGIO SILVA

Contact Information

Contractor Areio Inc; Lic. No.: 997015-B 73 NIGHTHAWK      IRVINE, CA 92604

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 4/15/2021 Approved KIRK LINKLATER
Bottom/Toe 4/19/2021 Partial Approval MATTHEW JENKINS
Bottom/Toe 6/3/2021 Partial Inspection JONATHAN HOM
Excavation 6/3/2021 Partial Approval JONATHAN HOM
Deputy Grading 6/7/2021 Approved KIRK LINKLATER
Bottom/Toe 6/8/2021 Partial Approval BRIAN OLSON
Excavation 6/8/2021 Partial Approval BRIAN OLSON
Bottom/Toe 6/10/2021 Partial Approval JONATHAN HOM
Excavation 6/10/2021 Partial Approval JONATHAN HOM
Deputy Grading 6/14/2021 Approved KIRK LINKLATER
Approved Compaction Report 7/16/2021 Approved AL GAMBLE
Bottom/Toe 10/25/2022 Approved AL GAMBLE
Final 10/25/2022 Permit Finaled AL GAMBLE
Rough 10/25/2022 Approved AL GAMBLE