12731 W EVANSTON ST 90049

Certificate Information: 12731 W EVANSTON ST 90049

Application / Permit
20030-30000-03247
Plan Check / Job No.
B20WL02658
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
Site grading for new SFD and retaining wall including R&R BF 200061 APPROVED FOR AN EXPORT OF 4,935 CUBIC YARDS
Permit Issued
Issued on 4/19/2021
Issuing Office
Current Status
Permit Finaled on 11/14/2024

Permit Application Status History

Submitted 6/24/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 REZA HAGHIGHAT
Corrections Issued 7/20/2020 REZA HAGHIGHAT
Quality Review Completed 7/27/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 7/27/2020 APPLICANT
Plan Check Approved 3/8/2021 REZA HAGHIGHAT
Issued 4/19/2021 APPLICANT
Permit Finaled 11/13/2024 JOHNNY MIRANDA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/16/2020 REZA HAGHIGHAT
Haul Route Cleared 1/13/2021 VERONICA LOPEZ

Contact Information

Contractor A J Engineering & Construction Inc; Lic. No.: 514600-B 4554 ELLENITA AVE      TARZANA, CA 91356
Engineer White,, William Michael; Lic. No.: C62111 19619 MATHILDE LN      SAUGUS, CA 91350
Geologist , ; Lic. No.: GEO2022 31129 VIA COLINAS   SUITE 707    WESTLAKE VILLAGE, CA 91362
Geologist Hollingsworth,, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 5/18/2021 Partial Approval BRIAN OLSON
Deputy Grading 6/2/2021 Approved BRIAN OLSON
Deputy Grading 6/3/2021 No Access for Inspection BRIAN OLSON
Special/Order Compliance 6/7/2021 Partial Inspection BRIAN OLSON
Deputy Grading 6/9/2021 Corrections Issued BRIAN OLSON
Deputy Grading 6/10/2021 Conditional Approval BRIAN OLSON
Bottom/Toe 6/24/2021 Partial Approval BRIAN OLSON
Special/Order Compliance 7/9/2021 Corrections Issued BRIAN OLSON
Sub-Drain 11/2/2021 Partial Approval CHARLES POWELL
Special/Order Compliance 11/29/2021 Partial Approval CHARLES POWELL
Bottom/Toe 12/3/2021 Partial Approval CHARLES POWELL
Bottom/Toe 1/20/2022 Not Ready for Inspection CHARLES POWELL
Drainage Devices/Catch Basin 10/6/2022 Not Ready for Inspection CHARLES POWELL
Sub-Drain 10/6/2022 Partial Approval CHARLES POWELL
Drainage Devices/Catch Basin 10/13/2022 Partial Approval MICHAEL TEMPLE
Drainage Devices/Catch Basin 10/24/2022 Partial Approval CHARLES POWELL
Drainage Devices/Catch Basin 10/28/2022 Partial Approval CHARLES POWELL
Approved Compaction Report 11/12/2024 Approved VASIL MIHALEV
Bottom/Toe 11/13/2024 Approved JOHNNY MIRANDA
Final 11/13/2024 Permit Finaled JOHNNY MIRANDA
Rough 11/13/2024 Approved JOHNNY MIRANDA